27 Jun 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

27 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100011397

Delivery and registration

When is the project declared for completion?

INDRADHANU RESIDENCY is registered with MahaRERA as P52100011397 and the promoter has declared completion for 27 Jun 2019.

27 Jun 2019

declared completion

87months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100011397
Registered on31 Aug 2017
Promoter-declared completion27 Jun 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for INDRADHANU RESIDENCY record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Team Associates is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for INDRADHANU RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
INDRADHANU RESIDENCY A WING1G+5-
INDRADHANU RESIDENCY B WING1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Haveli, Pune, 411015. Per the filed land record, the plot is bounded to the north by PROPERTY OF SHIVAJI B GAIKWAD, to the south by 15 FT ROAD AND VISHNU GAIKWAD, to the east by 15 FT ROAD and to the west by 5 FT ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)6 km
Pune Junction / city centre10 km
Kharadi / EON IT Park10 km
Baner–Balewadi belt12 km
Magarpatta / Hadapsar IT12 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhanori

Murli Manohar Heights
possession by Sep 2026 · Padmanabh Associates
Yash Grecia- E Wing
possession by Sep 2026 · Akshay Enterprises
Aaiji Crystal Phase I
possession by Oct 2026 · Aaiji Developers
Aaiji Crystal Phase II
possession by Oct 2026 · Aaiji Developers
Galaxy Co-Operative Housing Society Ltd
possession by Oct 2026 · Yash Developers
Austin
possession by Dec 2026 · Krishna Venture Skyscraper LLP

Major developers building in Dhanori

Other RERA-registered projects in Pune

Indralok Nagari
declared completion Apr 2024 · Yavat Realty
Indraprast Phase II Building NO A
declared completion Dec 2022 · Dattatray Hanumant Borade
Indraprasth
possession by Dec 2026 · J V Buildcon
Indraprasth Residency
declared completion Feb 2022 · R.r.builders & Developers
Indraprastha
declared completion Feb 2021 · Omkar Developers
Indraprastha
possession by Mar 2027 · Pranesh Homes LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026