Ingole Elite Phase 1

P52100018900 · Jalochi · promoter Rajendra Vasantrao Ingole

Certificate SignedDue 30 Sep 2021

Delivery & Registration

MahaRERA registrationP52100018900
Registered on11 Dec 2018
Promoter-declared completion30 Sep 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rajendra Vasantrao Ingole is the promoter of record on 38 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Row Houses1G+130 Sep 2020

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000026953003/10/2023Hemant Deshmukh vs Rajendra Ingoleorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202030 Sep 2021The project is completed and process for obtaining NOCs to apply for completion certificate is underway. But due to Covid-19 pandemic outburst and subsequent lockdown and change in

Location, Land & Connectivity

Located at Jalochi, Jalochi MIDC Road, Baramati, Pune, 413102. Per the filed land record, the plot is bounded to the north by Gat No 194 195, to the south by Gat No 189 190 191, to the east by Gat No 192 196 and to the west by 45 Mtr Wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rajendra Vasantrao Ingole is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Rajendra Vasantrao Ingole

Rajendra Vasantrao Ingole
Not filing quarterly progress reportsPune

Other RERA-registered projects in Baramati

Nirvana Elite
possession by Jul 2026 · Akash Jayesh Associates
Sharada Baug
possession by Aug 2026 · Mandar Shrikant Sikachi
G G Capital
possession by Aug 2026 · GG Builders AND Developers
Mayureshwar Icon
possession by Sep 2026 · Mayureshwar Reality AND Developers
Gadhavenanaware Heights
possession by Sep 2026 · Shri Developers
Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon

Major developers building in Baramati

Other RERA-registered projects in Pune

Ingole Icon
declared completion Dec 2025 · Ingole Construction
Innara Residency
declared completion Dec 2022 · Siddhidata Developers
Insignia
declared completion Dec 2018 · Gaikwad Girme Properties
Insignia
declared completion Dec 2020 · Atharva Realtors
Insignia Building A
declared completion Dec 2022 · Vinode Developers
Insignia - Phase II
declared completion Dec 2018 · M/s. K N Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026