JAI GANESH ENCLAVE

Chikhali · LMK ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100012772

Delivery and registration

When is the project declared for completion?

JAI GANESH ENCLAVE is registered with MahaRERA as P52100012772 and the promoter has declared completion for 30 Jun 2018.

30 Jun 2018

declared completion

99months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100012772
Registered on07 Sep 2017
Promoter-declared completion30 Jun 2018
Current statusCertificate Signed
Against todayabout 99 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JAI GANESH ENCLAVE record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JAI GANESH ENCLAVE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
JAI GANESH ENCLAVE1G+730 Jun 2018

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for JAI GANESH ENCLAVE, with orders passed in 7 of them.

7complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000004361311/11/2019Avinash Gaikwad vs Sunil Lokhandeorder passed
CC00500000004372230/11/2019Mr Dinesh Bhimrao Badode vs M/s LMK Associates a partnership firm through its partnersorder passed
CC00500000004372330/11/2019Mrs Pushpa Mohan Jadhav vs M/s LMK Associates a partnership firm though its partnersorder passed
CC00500000004372430/11/2019Mr.Pramod Dnyandev Shende vs M/s LMK associates a partnership firm though its partnersorder passed
CC00500000004372530/11/2019Mrs.Vaishali Manoj Deshmane vs M/s LMK associates a regi partnershipfirm though its partnersorder passed
CC00500000004372630/11/2019Mr Shidray Shrimanat Kalshetti vs m/s LMK associates through its partnersorder passed
CC00500000004372730/11/2019Mr.Subhash Balasaheb Sandbhor vs M/s LMK associates through its partnersorder passed

Location, Land & Connectivity

Located at Chikhali, Haveli, Pune, 412114. Per the filed land record, the plot is bounded to the north by REMAINING PROPERTY OF GAT NO 379, to the south by ROAD, to the east by PROPERTY OF MR SUNIL LOKHANDE and to the west by PROPERTY OF MR KALURAM SALUNKHE AND OTHERS. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park13 km
Baner–Balewadi belt14 km
Pune Int'l Airport (Lohegaon)14 km
Pune Junction / city centre17 km
Kharadi / EON IT Park18 km
Magarpatta / Hadapsar IT20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chikhali

Prasanna Paradise
possession by Sep 2026 · Paras Properties
Adhya Radhakrishna C Wing
possession by Oct 2026 · Adhya Properties
Aishwaryam ONE Moshi
possession by Dec 2026 · SAI Essen Developers
Apna Market
possession by Dec 2026 · Universal Developments
Ganesh Paradise Phase 2
Not filing quarterly progress reports · possession by Dec 2026 · Ekdanta Nest LLP
Ganesh Siddhi E Wing
possession by Dec 2026 · Ganeshconstruction

Other RERA-registered projects in Pune

JAI Ganesh Residency
declared completion Dec 2021 · JAI Ganesh Developers
Jai Proposed Building At CTS No. 1113/a, Subhash Nagar,shukrawar Peth,pune
possession by Dec 2026 · Pleasant Spaces LLP
Jaijinendra Nilay
possession by Jun 2030 · Jaijinendra Shreekalp
Jainoday
declared completion May 2024 · Jainoday Buildcon
Jalasampada
possession by Nov 2027 · Param Nilay Constructions LLP
Jalvan Homes Phase - I
possession by Dec 2028 · Mompaasons LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026