MahaRERA Property Intelligence · Pune

Jaydeep Heights

P52100045282 · SASWAD · promoter Gurudatta Developers

Certificate SignedDue 15 Mar 2024

Delivery & Registration

MahaRERA registrationP52100045282
Registered on12 May 2022
Promoter-declared completion15 Mar 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Gurudatta Developers is the promoter of record on 22 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Jaydeep Heights1G+415 Mar 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SASWAD, SASWAD, Purandhar, Pune, 412301. Per the filed land record, the plot is bounded to the north by Survey no 68-2, to the south by 9 meter wide internal road, to the east by Adjacent Plot no 7 and to the west by Adjacent Plot no 9. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Saswad

Bliss Fields-Phase-I
possession by Oct 2026 · SAI Shraddha Venture
Karha Vastu
possession by Nov 2026 · S J Developers
Venkatesh Pushpakala
Not filing quarterly progress reports · possession by Dec 2026 · Sanjay Dnynoba Jagtap
Anand Baug C Wing
possession by Dec 2026 · Sankalp Developers
Kanishka Grand Plaza
possession by Dec 2026 · Platinum Lifespace Developers
Kanishka Grand Plaza Max
Not filing quarterly progress reports · possession by Dec 2026 · Platinum Lifespace Developers

Major developers building in Saswad

Other RERA-registered projects in Pune

Jayhind Ample
possession by Apr 2027 · Jayhind Group Builders
Jayhind Hillside
declared completion Mar 2024 · Sagar Jaysing Erande
Jayhind Icon
declared completion Jan 2020 · Jayhind Builders AND Developers
Jayka Synergy Tower
possession by Dec 2028 · Baner Pashan 5 Realty LLP
Jaymala Business Court
declared completion Apr 2019 · Satyam Constructions
Jayraj 4 Square
possession by Sep 2027 · JAY Nanaso Patil

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026