MahaRERA Property Intelligence · Pune

KRISHNA ANGAN

P52100005605 · promoter Krishna Developers

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52100005605
Registered on11 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A WING1G+4-
B WING1G+2-
C WING1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Jagdale Court Pune352/20172017In Progress

Location, Land & Connectivity

Located at Haveli, Pune, 411012. Per the filed land record, the plot is bounded to the north by CT NO 2256, to the south by CT S NO 2235, to the east by CT S 2234 and to the west by CT S NO 2243. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt7 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)9 km
Hinjewadi Rajiv Gandhi IT Park10 km
Kharadi / EON IT Park12 km
Magarpatta / Hadapsar IT13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Krishna Developers is the promoter on 13 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Krishna Developers project & its RERA track record →

Other flagged projects by Krishna Developers

Other RERA-registered projects in Dapodi

Avalon City - C5 And C6
possession by Mar 2027 · Classic Promoters And Builders Private L
Avalon City - C2
possession by Jul 2027 · Classic Promoters And Builders Private L
Horizon Harmony
possession by Dec 2027 · Ramgeet Developers
SAI Bliss
possession by Dec 2027 · SAI Ventures
Mayur Skylife
possession by Dec 2030 · Bunty Homes
Ganesh Samruddhi B Wing
Not filing quarterly progress reports · declared completion Dec 2025 · Ganeshconstruction

Major developers building in Dapodi

Other RERA-registered projects in Pune

Krishna Business Centre
declared completion Sep 2020 · Vrisa Infotech PVT LTD
Krishna Classic
declared completion Jul 2024 · Kwality Developers
Krishna Classic
declared completion Dec 2019 · Pandurang Maruti Kalokhe
Krishna Dham
declared completion Jul 2019 · Ikon Developer
Krishna Dham
declared completion Jun 2023 · Ikon Developers
Krishna Heights
declared completion Dec 2025 · Narayan Dharmaji Bodke

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026