MahaRERA Property Intelligence · Pune

KRISHNAKAMAL RESIDENCY

P52100016876 · Sangurdi · promoter Bsk Group

Certificate SignedDue 01 Jun 2022

Delivery & Registration

MahaRERA registrationP52100016876
Registered on20 Jun 2018
Promoter-declared completion01 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
C wing1G+801 Jun 2021
D wing1G+801 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
01 Jun 202201 Jun 2023Site was completed within due date as granted or allowed as per Maharera rules. However, it got delayed due to non-receipt of completion/occupancy certificate from the PMRDA author

Location, Land & Connectivity

Located at Sangurdi, Induri-Dehu Road, Mulshi, Pune, 412109. Per the filed land record, the plot is bounded to the north by 246, to the south by Road, to the east by 247 and to the west by 244-245. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park15 km
Baner–Balewadi belt18 km
Pune Int'l Airport (Lohegaon)24 km
Pune Junction / city centre25 km
Kharadi / EON IT Park28 km
Magarpatta / Hadapsar IT30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dehu

Radhika Residency
possession by Aug 2026 · Mybhoomi Vastuspace
Trimurti Santkrupa Heights
possession by Aug 2026 · Sambhaji Baban Borhade
Gathagram Sector 2
possession by Nov 2026 · Harit Landmarks LLP
Gathagram Sector 4 Phase 1
possession by Nov 2026 · Harit Landmarks LLP
Gathagram Sector 5 Phase 1
possession by Nov 2026 · Harit Landmarks LLP
Dwarkadheesh Residency
Not filing quarterly progress reports · possession by Dec 2026 · Harichandra Rambhau Satav

Other RERA-registered projects in Pune

Krishnakunj
declared completion Dec 2024 · Gokhale Buildcon LLP
Krishnakunj Phase 1
declared completion Dec 2025 · Heera Devlopers
Krishnakunj Phase 2
possession by May 2028 · Heera Devlopers
Krishnakunj Residency
possession by Mar 2029 · Kedar Associates
Krishnanayan
declared completion Dec 2021 · Gokhale Realty LLP
Krishnas Blessing A, B, C Building
declared completion Aug 2019 · Vishal Infracon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026