MahaRERA Property Intelligence · Pune

LUMINARE HEIGHTS

P52100030987 · Lipane Wasti · promoter Darsheel Group

Certificate SignedDue 31 Jan 2025

Delivery & Registration

MahaRERA registrationP52100030987
Registered on29 Sep 2021
Promoter-declared completion31 Jan 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Darsheel Group is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Wing A1G+6-
Wing B1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Jul 202431 Jan 2025We M/s Darsheel Group hereby declare that the Extension of project status because the on-going project information is change & Extra floor work is added in new revised sanction pl

Location, Land & Connectivity

Located at Lipane Wasti, Jambhulwadi Road, Haveli, Pune, 411046. Per the filed land record, the plot is bounded to the north by House of Ramdas Lashkare, to the south by Property of Sudam and Mahendra Sopan Lipane, to the east by 50 Ft Jambhulwadi Road and to the west by Pazar Talav. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~44 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Baner–Balewadi belt44 km
Hinjewadi Rajiv Gandhi IT Park44 km
Pune Junction / city centre49 km
Magarpatta / Hadapsar IT53 km
Kharadi / EON IT Park56 km
Pune Int'l Airport (Lohegaon)56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Katraj

Aishwarya Heights
possession by Jul 2026 · Shree Sadguru Construction
Basil Chandrakant
possession by Jul 2026 · Shree Sadguru Developers
Vastushree Phase-1
possession by Aug 2026 · Vastu Construction
Capella
possession by Aug 2026 · D K Realties
Divya Elite
possession by Aug 2026 · RRS Infracon LLP
Yogamrut
Not filing quarterly progress reports · possession by Aug 2026 · Jay Ganesh Buildcon

Major developers building in Katraj

Other RERA-registered projects in Pune

Lunawat Apex
declared completion Jun 2023 · Navya Prem Developers LLP
Lush Green
declared completion Jun 2022 · Pragati Constructions
Lush Residences
possession by Dec 2028 · Lush Residences LLP
Lushlife Impero Building C
possession by Dec 2030 · Lushlife Real Estate LLP
Lushlife OVO
declared completion Dec 2020 · Lushlife Properties LLP
Luxor
declared completion Feb 2024 · Gajanan Uttamrao Mante

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026