MahaRERA Property Intelligence · Pune

MAITRI NEST

P52100023069 · DIGHI · promoter Developers

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP52100023069
Registered on22 Nov 2019
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
MAITRI NEST A BLDG1G+631 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at DIGHI, DIGHI, Haveli, Pune, 411015. Per the filed land record, the plot is bounded to the north by PRIVATE PLOT NO 84 AND PART OF S NO 18 2 2, to the south by ROAD, to the east by PART OF S NO 18 2 2 and to the west by PRIVATE POT HISSA NO 82. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~65 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park65 km
Baner–Balewadi belt67 km
Pune Junction / city centre77 km
Magarpatta / Hadapsar IT82 km
Pune Int'l Airport (Lohegaon)83 km
Kharadi / EON IT Park84 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M K Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by M K Developers

Other RERA-registered projects in Dhanori

Gada Elina
possession by Jul 2026 · Kubix Realties LLP
Belmont Aster
possession by Aug 2026 · Prakash Ganpatrao Kshirsagar
Belmont Jasmine
possession by Aug 2026 · Uttam Nivrutti Dimbale
Murli Manohar Heights
possession by Sep 2026 · Padmanabh Associates
Yash Grecia- E Wing
possession by Sep 2026 · Akshay Enterprises
Aaiji Crystal Phase I
possession by Oct 2026 · Aaiji Developers

Major developers building in Dhanori

Other RERA-registered projects in Pune

Maitri Park
possession by Jul 2027 · Shree Constructions
Maitri Park Sahakari Gruharachana Sanstha Maryadit
declared completion Dec 2024 · Maitri Park CO Operative Housing Society
Maitri Residency
declared completion Dec 2025 · Dhamale Thorat Associates
Maitri Vishwa
possession by Dec 2030 · Vishwa Landmarks LLP
Majestic Pearl
declared completion May 2022 · Vikas Narayan Virkar
Majestic Pride
declared completion Oct 2020 · Majestic Builders & Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026