MahaRERA Property Intelligence · Pune

Manik Villa

P52100027391 · SINGHGAD ROAD · promoter Samarth Associates

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP52100027391
Registered on08 Dec 2020
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Building 21G+731 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SINGHGAD ROAD, SINGHGAD ROAD, Haveli, Pune, 411051. Per the filed land record, the plot is bounded to the north by S NO 3, to the south by Building No 1, to the east by S NO 3 and to the west by S No 3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Samarth Associates is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Samarth Associates

Other RERA-registered projects in Hingane Khurd

Sai Ganesh Vihar D Wing
possession by Nov 2026 · Jayshree Developers
Aura Waters Phase -I
possession by Dec 2026 · Ranawat Properties
Sunder Srushti Wing D6
possession by Dec 2026 · Suresh Dharmavat AND Associates
Kanchan Heights
possession by Apr 2027 · Orbiz Estate
Venkatesh Skydale Phase 4
possession by Jun 2027 · Shree Venkatesh Buildcon
Park Life Wing C
possession by Mar 2028 · Kudale Patil AND Jadhav Ventures

Other RERA-registered projects in Pune

Manik Vishwa
declared completion Jun 2023 · Bagade And Patole Associates
Manikbaug Orchid
possession by Dec 2031 · Waghere Promoters
Manikdeep
possession by Oct 2027 · Not Available
Maniratna Complex
possession by Mar 2031 · Mansi Builders AND Developers
Manisha
possession by Jun 2028 · Belvalkar Housing LLP
Manisha
possession by Oct 2028 · Shri Laxmi Narayan Properties LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026