MahaRERA Property Intelligence · Pune

Mayur Samruddhi Phase - II D wing

P52100007199 · promoter Bunty Properties Unit

Certificate SignedDue 31 Jul 2028

Delivery & Registration

MahaRERA registrationP52100007199
Registered on17 Aug 2017
Promoter-declared completion31 Jul 2028
Current statusCertificate Signed
Against today24 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Bunty Properties Unit is the promoter of record on 9 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Wing D - 1st and 2nd Floor1G+131 Jul 2027
Wing D - 2nd to 5th Floor1G+431 Jul 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 411035. Per the filed land record, the plot is bounded to the north by Plot Of E Building, to the south by 18 mtr Road, to the east by Nala and to the west by 18 mtr D P Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park8 km
Baner–Balewadi belt10 km
Pune Int'l Airport (Lohegaon)17 km
Pune Junction / city centre17 km
Kharadi / EON IT Park20 km
Magarpatta / Hadapsar IT21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Akurdi

Pentagon Business HUB
possession by Sep 2026 · Cosmic Infrastructure
Mantra Meraki Phase 5
possession by Dec 2026 · Mantra Residential Akurdi Private Limite
Mantra Meraki Phase 6
possession by Dec 2026 · Mantra Residential Akurdi Private Limite
ONE Platinum
possession by Dec 2026 · Matrix Developers
Orchard Residences
possession by Dec 2026 · A & A Realtors
Vasant Estella
possession by Dec 2026 · Shrikrishna Wonder Properties

Major developers building in Akurdi

Other RERA-registered projects in Pune

Mayur Skylife
possession by Dec 2030 · Bunty Homes
Mayura
declared completion Jan 2026 · Badhekar Properties
Mayureshwar
declared completion Dec 2024 · Vaastu Vishwa Developers
Mayureshwar Classic A
possession by Jan 2029 · Mayureshwar Construction
Mayureshwar Heights
declared completion May 2025 · Akshay Balaso Kamthe
Mayureshwar Icon
possession by Sep 2026 · Mayureshwar Reality AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026