Maza Gharkul

Sanaswadi · Swaraa Groups

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

66units filed as unsoldInventory · 12 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
92registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100000081

Delivery and registration

When is the project declared for completion?

Maza Gharkul is registered with MahaRERA as P52100000081 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100000081
Registered on28 Jun 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Maza Gharkul record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Swaraa Groups is the promoter of record on 6 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Maza Gharkul, 26 of 92 homes filed with MahaRERA are recorded as sold or booked, about 28%, and 66 remain available.

28%sold

26 of 92 homes

₹2.71 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹1.98 Cr (about 73%) is recorded as collected and ₹72.99 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 26 registered agreements, the effective carpet rate is ₹4,689/sqft, with eight in ten falling between ₹3,164 and ₹5,245 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 26 homes carry one, and 66 of the 92 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
106158 sqftRs 7.44 lakh typical, over Rs 5.00 lakh to Rs 8.00 lakh11 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In Maza Gharkul, 46 of the 66 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 65 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 92 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A1G+63231 Dec 2020
B1G+62830 Jun 2021
C1G+832-

Unit mix on the filing: 92 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Maza Gharkul, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000010654706/08/2022KISHOR Dattatraya Karanjule vs SUBHASH DAHIPHALEorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Dear Sir, Our project got delayed due stoppage of work in lockdown of COVID-19 pandemic and also due shortage of material supply and price inflation. So we request you to grant
30 Jun 202231 Dec 2025Dear Sir, Or project got delayed to stoppage of work in lockdown of COVID-19 Pandemic, due to shortage of labour and material supplies and price inflation, due delay or default

Location, Land & Connectivity

Located at Sanaswadi, Pune-Nagar Highway, Haveli, Pune, 412208. Per the filed land record, the plot is bounded to the north by Gat No 1533, to the south by Gat No 1524 1526-29 1531, to the east by Road and to the west by Rivulet -Odha. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~55 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park55 km
Pune Int'l Airport (Lohegaon)55 km
Magarpatta / Hadapsar IT58 km
Pune Junction / city centre62 km
Baner–Balewadi belt69 km
Hinjewadi Rajiv Gandhi IT Park72 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shikrapur

Sharanya Galaxy
possession by Dec 2026 · Sharanya Constructions
Harmony
possession by Dec 2026 · Nandakumar Lapalikar
Abhilasha Wing A AND Wing B
possession by Dec 2026 · M/S Kudale Sable Builders
Maitri Gold
possession by Dec 2026 · Maitri Developers AND Builders
Patil Plaza
Not filing quarterly progress reports · possession by Dec 2026 · Devidas Patil
Rustic Meadows
possession by Dec 2026 · Sanjay Gopichand Jasuja

Major developers building in Shikrapur

Other RERA-registered projects in Pune

Maza Gharkul Karegaon
declared completion Nov 2020 · Kuber Properties
MBM Orbit
declared completion Sep 2026 · SAI Sankalp Developers
Meadows Heritage
declared completion Mar 2022 · Nagpal Buildcon PVT LTD
Meander Wing A
declared completion Sep 2024 · Eastend Spaces LLP
Meander Wing C
possession by Dec 2026 · Eastend Spaces LLP
Medha
possession by Dec 2028 · D & T Properties

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026