Plotted Development Intelligence · Pune

Mhalsakant Sakharam Peshave

P52100047760 · jejuri rural · promoter Mhalasakant Sakharam Peshave

Certificate SignedDue 30 Jun 2027

Delivery & Registration

MahaRERA registrationP52100047760
Registered on28 Nov 2022
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today11 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000026957912/10/2023Rajendra khanderao Peshve vs MHALSAKANT SAKHARAM PESHVEpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202430 Jun 2027Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an e

Location, Land & Connectivity

Located at jejuri rural, jejuri rural, Purandhar, Pune, 412303. Per the filed land record, the plot is bounded to the north by Jejuri saswad Road, to the south by Gat 813-800, to the east by Gat 844 part and to the west by Gat 845. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jejuri

Savali Plaza
possession by Dec 2026 · Savali Associates
Krishnachhaya
Not filing quarterly progress reports · possession by Dec 2026 · Shri Dattaprabhu Construcction
Malhar Resisdency
Not filing quarterly progress reports · possession by Dec 2026 · JAI Malhar Promoter AND Developers
Purandar Plaza
possession by Dec 2026 · Shri Hari Om Constructions
JAY Shankar Complex
possession by May 2027 · Arun Shankar Joshi
Malhargad View
possession by Oct 2027 · Harinima Builders

Other RERA-registered projects in Pune

Mi Casa
declared completion Sep 2024 · Marimagnum Constructions
Mi Casa Primaliva
declared completion Jun 2025 · Shree Venkatesh Associates
Miami-A1-A2-A3-B2
possession by Dec 2029 · Pride Builders LLP
Miami A4-A5
possession by Dec 2029 · Pride Builders LLP
Miami A6-A7-B1
possession by Dec 2028 · Pride Builders LLP
Micasaa Phase 2
declared completion Mar 2022 · Gagan Global Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026