MahaRERA Property Intelligence · Pune

Mont Vert Yolo

P52100007210 · Bhugaon · promoter Mont Vert Elegance

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52100007210
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mont Vert Elegance is the promoter of record on 10 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Building A1G+1430 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Bhugaon, Mont Vert Drive, Haveli, Pune, 411042. Per the filed land record, the plot is bounded to the north by S No 10 H No 2 p, to the south by S No 11 and main road, to the east by By Road and S No 9 and to the west by S No 10 p. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt7 km
Hinjewadi Rajiv Gandhi IT Park10 km
Pune Junction / city centre14 km
Magarpatta / Hadapsar IT19 km
Pune Int'l Airport (Lohegaon)20 km
Kharadi / EON IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mont Vert Elegance is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mont Vert Elegance project & its RERA track record →

Other flagged projects by Mont Vert Elegance

Other RERA-registered projects in Ghorpade Peth

Sanghvi Premio
possession by Oct 2026 · Nitin Kantilal Sanghvi
Samaira Tower
possession by Nov 2026 · Prathamesh Constro Realty Llp
Shri Balaji Sudarshan
Deregistered by MahaRERA · possession by Dec 2026 · Shri Balaji Sudarshan
Radiance
Not filing quarterly progress reports · possession by Dec 2026 · Mohammed Sabir Husain Shaikh
Shree Swami Krupa Sadan
possession by Dec 2026 · A S Associates
Siddhi Plaza
possession by Dec 2026 · Shree Developers

Major developers building in Ghorpade Peth

Other RERA-registered projects in Pune

Montage
possession by Dec 2026 · Golden Kalash Housing LLP
Montaire
possession by Dec 2029 · Atrium Landmarks LLP
Montclaire
declared completion Dec 2024 · Niraj Kumar Associates Pvt Ltd
Monte Rosa
declared completion Dec 2023 · Tushar Builders & BKP Infra LLP
Montecito Phase I - D Building Part 2
declared completion Dec 2018 · Amit Vastu Ventures LLP
Montecito Phase II - E Building
declared completion Dec 2021 · Amit Vastu Ventures LLP

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026