Pune/Project record

MahaRERA · the public record

NANDAN ASPIRA

Aundh · SHAMKANT KESHAV KOTKAR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100000971

Delivery and registration

When is the project declared for completion?

NANDAN ASPIRA is registered with MahaRERA as P52100000971 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

71months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100000971
Registered on25 Jul 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 71 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NANDAN ASPIRA record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shamkant Keshav Kotkar is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NANDAN ASPIRA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
NANDAN ASPIRA1G+1122 May 2020

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for NANDAN ASPIRA, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000025906022/07/2023M/s Bora Finance Corporation vs M/s. Nandan Buildersorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020As there was poor response on sales front, the project was converted into commercial building. With consent of the customers we have achieved sanction of the project as commercial
30 Apr 202030 Apr 2020CONSTRUCTION ACTIVITY NOT COMPLETED DUE TO POOR SALES.HOWEVER 90% CONSTRUCTION IS COMPLETED BY OUR OWN FUNDS AND PART SALES OF FLATS (ONLY THREE OUT OF NINE.)

Location, Land & Connectivity

Located at Aundh, Pune City, Pune, 411007. Per the filed land record, the plot is bounded to the north by SURVEY NO 164 PART AND VATSALYAVIHAR, to the south by 18 MTR WIDE DP ROAD, to the east by SURVEY NO 165 PART and to the west by 9 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt3 km
Hinjewadi Rajiv Gandhi IT Park8 km
Pune Junction / city centre8 km
Pune Int'l Airport (Lohegaon)12 km
Magarpatta / Hadapsar IT14 km
Kharadi / EON IT Park14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Aundh

Geras Affinia
possession by Dec 2026 · Gera Developments Private Limited
Udyam Nagari
possession by Dec 2026 · MAP Associates
Avanti Park
possession by Dec 2026 · Saachee Buildcon
Brain Matrix
possession by Dec 2026 · M/s Bora Associates
Ruhi Mangalam Niyoshi
possession by Dec 2026 · Ruhi Mangalam Associates
Sanjeevan
possession by Dec 2026 · Badhekar & Pitale Projects LLP

Major developers building in Aundh

Other RERA-registered projects in Pune

Nandan Fortura
declared completion Mar 2023 · Nandan Associates
Nandanvan
declared completion Jun 2019 · Pandit Javdekar Associates
Nandanvan
declared completion Oct 2019 · Nitin Govind Sable
Nandanvan
possession by Dec 2028 · NG Rathi Construction Private Limited
Nandanvan
possession by Dec 2027 · Balaji Promoters
Nandanvan Colina
declared completion Jun 2026 · SAI Sankalp Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026