NARAYAN COMPLEX B

HINGANE (KD) · N K Jagtap Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014882

Delivery and registration

When is the project declared for completion?

NARAYAN COMPLEX B is registered with MahaRERA as P52100014882 and the promoter has declared completion for 30 Jun 2021.

30 Jun 2021

declared completion

63months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014882
Registered on09 Jan 2018
Promoter-declared completion30 Jun 2021
Current statusCertificate Signed
Against todayabout 63 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NARAYAN COMPLEX B record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jagtap Developers is the promoter of record on 62 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

62projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NARAYAN COMPLEX B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
B1G+230 Sep 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021We cannot complete this project within declared date 30/09/2019 submitted in From B at the time of making application for registration of the said project . The reason For the exte

Location, Land & Connectivity

Located at HINGANE (KD), SINHGAD ROAD, Haveli, Pune, 411051. Per the filed land record, the plot is bounded to the north by BROOKS, to the south by INTERNAL ROAD, to the east by REMAINING PORTION OF SAID SERVEY NUMBER and to the west by PROPERTY OF SHRI KADU AND OTHERS. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre7 km
Baner–Balewadi belt10 km
Magarpatta / Hadapsar IT11 km
Kharadi / EON IT Park14 km
Pune Int'l Airport (Lohegaon)15 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

N K Jagtap Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Dhayari

Sai Ganesh Vihar D Wing
possession by Nov 2026 · Jayshree Developers
Aura Waters Phase -I
possession by Dec 2026 · Ranawat Properties
Kanchan Heights
possession by Apr 2027 · Orbiz Estate
Venkatesh Skydale Phase 4
possession by Jun 2027 · Shree Venkatesh Buildcon
Park Life Wing C
possession by Mar 2028 · Kudale Patil AND Jadhav Ventures
Aura Waters Phase II
possession by Dec 2029 · Ranawat Properties

Other RERA-registered projects in Pune

Narayan Octave Commercial
declared completion Dec 2019 · Anil Ratanlal Agrawal
Naren Bliss And Naren Pearl
declared completion Dec 2023 · Nucon Builders
Narendra Housing Society
declared completion Sep 2026 · Elite Infrastructure PVT LTD
Narmada
possession by Jun 2027 · Moraya Associates
Narmada Blue Sapphire
declared completion Jul 2025 · Tanaji Ramchandra Katke
Narsinh Residency
declared completion Aug 2019 · Narsinh Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026