Pune/Project record

MahaRERA · the public record

Neelkanth Business Park

Daund · Nexus Buildcon

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100025316

Delivery and registration

When is the project declared for completion?

Neelkanth Business Park is registered with MahaRERA as P52100025316 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100025316
Registered on10 Apr 2020
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Neelkanth Business Park record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Nexus Buildcon is the promoter of record on 41 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

41projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Neelkanth Business Park in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Commercial1G+331 Dec 2021
Residential1G+531 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Daund, Daund Patas 24 m wide DP Road, Daund, Pune, 413801. Per the filed land record, the plot is bounded to the north by CTS No 2727 Part, to the south by Daund Patas DP Road, to the east by CTS No 2727 Part and to the west by CTS No 2727 Part. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Daund

Shri Ashtavinayak Park
possession by Oct 2026 · Ajay Builders AND Associates Daund
Sai Capital
Not filing quarterly progress reports · possession by May 2027 · Satish Deepak Thorat
R City
possession by Mar 2028 · Reva Construction AND Developers
Shri Govind Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Developers Daund
Shri Hari Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Construction AND Developers Daund
Ekdanta
possession by Dec 2028 · M/S Prakash Construction Co.

Other RERA-registered projects in Pune

Neelkanth Complex
declared completion Sep 2023 · Ajay Nanasaheb Jadhavrao
Neelkanth Landmarks Shreeniwas Residency
declared completion Mar 2026 · Neelkanth Landmarks
Neelkanth Residency
declared completion Jun 2019 · Shivshakti Associates
Neelkanth Residency Phase - II
declared completion Dec 2024 · Shivshakti Associates
Neelratna
possession by Oct 2029 · Kotibhaskar Infrastructures &develop
Neera City Centre
declared completion Jul 2023 · Avaneesh Infra.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026