MahaRERA Property Intelligence · Pune

PANT SARATHI BUILDERS LLP

P52100011830 · Pimple gurav · promoter Pantsarathi Builders Llp

Certificate SignedDue 31 Dec 2028

Delivery & Registration

MahaRERA registrationP52100011830
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
SARATHI PRIDE1G+331 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
15 Mar 202415 Sep 2023REASON FOR DELAY IS DUE TO COVID-19 THATS WHY ITS GETTING LATE TO THE COMPLETION PROCESS.COMPLETION DATE OF PROJECT WAS 30-09-2020 BUT WE WANT IT CHANGED AS 15-09-2023.
15 Mar 202430 Mar 2020FINAL FINISHING WORK FOR PROJECT IS UNDER PROGRESS NEED SOME TIME TO FINISH THIS WORK SO KINDLY PROCESS MY REQUEST OF PROJECT EXTENSION AS SOON AS POSSIBLE....
31 Mar 201931 Dec 2028Due to revise Sanction

Location, Land & Connectivity

Located at Pimple gurav, Sr no 78, Haveli, Pune, 411007. Per the filed land record, the plot is bounded to the north by SURVEY NO 78 1 PART, to the south by SURVEY NO 78 3, to the east by SURVEY NO 78 2 PART and to the west by ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt7 km
Hinjewadi Rajiv Gandhi IT Park8 km
Pune Junction / city centre12 km
Pune Int'l Airport (Lohegaon)13 km
Kharadi / EON IT Park16 km
Magarpatta / Hadapsar IT17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Aundh

Saachee Elite
possession by Aug 2026 · Suyog Suryakant Chhajed
Geras Affinia
possession by Dec 2026 · Gera Developments Private Limited
Udyam Nagari
possession by Dec 2026 · MAP Associates
Avanti Park
possession by Dec 2026 · Saachee Buildcon
Brain Matrix
possession by Dec 2026 · M/s Bora Associates
Ruhi Mangalam Niyoshi
possession by Dec 2026 · Ruhi Mangalam Associates

Major developers building in Aundh

Other RERA-registered projects in Pune

Papa Imperio
declared completion Dec 2019 · Anup Indrapal Bashani
Papa Mamta Residency
declared completion Jun 2019 · Anup Indrapal Bashani
Paradigam Vandan
possession by Feb 2028 · Paradigm Developers Private Limited
Paradise
declared completion Jun 2024 · Amarnath Buildcon
Paradise - B2 And B3
declared completion Jun 2026 · Kevin Properties
Paradise Co- Operative Housing Society
possession by Dec 2027 · Kakade Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026