Pune/Project record

MahaRERA · the public record

PARISHREYA

MALAVALI · NEW FRONT PRABHAVEE VENTURES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100008303

Delivery and registration

When is the project declared for completion?

PARISHREYA is registered with MahaRERA as P52100008303 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100008303
Registered on18 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARISHREYA record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

New Front Prabhavee is the promoter of record on 4 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARISHREYA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
A BUILDING1G+1-
B BUILDING1G+1-
C BUILDING1G+1-
D BUILDING1G+1-
E BUILDING1G+1-
F BUILDING1G+1-
G BUILDING1G+1-
H BUILDING1G+1-
TWIN BUNGLOW 1 AND 21G+1-
TWIN BUNGLOW 3 AND 41G+1-
TWIN BUNGLOW 5 AND 61G+1-
TWIN BUNGLOW 7 AND 81G+1-
TWIN BUNGLOW 9 AND 101G+1-
TWIN BUNGLOW 11 AND 121G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MALAVALI, SADAPUR , Pune City, Pune, 410502. Per the filed land record, the plot is bounded to the north by OPEN SPACE 2 AND 3 AND 4, to the south by GAT NO 260 261 262, to the east by INTERNAL ROAD and to the west by GAT NO 258. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park159 km
Baner–Balewadi belt164 km
Pune Int'l Airport (Lohegaon)173 km
Pune Junction / city centre174 km
Kharadi / EON IT Park177 km
Magarpatta / Hadapsar IT179 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

NEW Front Prabhavee Ventures is the promoter on 4 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by NEW Front Prabhavee Ventures

NEW Front Prabhavee Ventures
Past its declared completion datePune
NEW Front Prabhavee Ventures
Past its declared completion datePune
NEW Front Prabhavee Ventures
FlaggedPune

Other RERA-registered projects in Junnar

Shivai Sahakari Gruh Nirman Sanstha Maryadit
possession by Dec 2026 · Mayuresh Developers
Suryaprastha
possession by Dec 2026 · Suryaputra Developers
Vijayalaxmi Sulojay
possession by Dec 2026 · Shreevijayalaxmi Developers
Gulmohar Society
possession by Dec 2027 · Nitin Sitaram Kulkarni
Junnar Trade Center
Not filing quarterly progress reports · possession by Dec 2027 · Vastu Realty
Anand Sagar
Not filing quarterly progress reports · possession by May 2036 · Sunshine Associates

Other RERA-registered projects in Pune

Park Abhilasha- A,b,c Building
possession by Dec 2027 · Aaryan Developers
Park Abhilasha-D Building
possession by Dec 2027 · Aaryan Developers
Park Astra
declared completion Dec 2025 · Pride Purple Infrastructure
Park Astra Phase II
possession by Dec 2026 · Pride Purple Infrastructure
Park Connect
declared completion Dec 2023 · Pride Purple Infrastructure
Park Connect Phase II
declared completion Dec 2024 · Pride Purple Infrastructure

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026