Pune/Project record

MahaRERA · the public record

Playtor Paud C- Phase 2

Next to Tehsil Office · SANGAM REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100002910

Delivery and registration

When is the project declared for completion?

Playtor Paud C- Phase 2 is registered with MahaRERA as P52100002910 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100002910
Registered on04 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Playtor Paud C- Phase 2 record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sangam Realty is the promoter of record on 16 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Playtor Paud C- Phase 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
C21G+730 Jun 2019
C41G+730 Jun 2019

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Playtor Paud C- Phase 2, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000028996829/12/2023POOJA VILAS KULKARNI vs SANGAM REALTYorder passed
CC1250123414/04/2025ajay ramdas pardeshi vs SANGAM REALTYorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2020Due to delay in getting permissions of plinth checking certificate from PMRDA, Pune, we here request you that, we require 1 year extension for completion of our Playtor Paud C - Ph
29 Jun 202031 Dec 2021Attached list of Allottes have consented to extend Rera date of completion of the project form 29/12/2020 to 30/09/2022.
31 Dec 202130 Jun 2024request for commencement certificate and building material was shortaged

Location, Land & Connectivity

Located at Next to Tehsil Office, Paud-Mulshi Road, Pune City, Pune, 412108. Per the filed land record, the plot is bounded to the north by Remaining Land of Gat No 245, to the south by Adj Forest Property, to the east by Adj C1 Bldg of Phase 1 and to the west by Amenity Space. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park26 km
Baner–Balewadi belt28 km
Pune Junction / city centre38 km
Magarpatta / Hadapsar IT43 km
Pune Int'l Airport (Lohegaon)44 km
Kharadi / EON IT Park45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sangam Realty is the promoter on 5 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Sangam Realty project & its RERA track record →

Other flagged projects by Sangam Realty

Sangam Realty
Deregistered by MahaRERAPune
Sangam Realty
Deregistered by MahaRERAPune

Other RERA-registered projects in Paud

Playtor Paud D- Phase 2
Deregistered by MahaRERA · possession by Sep 2026 · Sangam Realty
Shivangan
possession by Nov 2026 · R M Developers Pune
Nishigandh, B Wing
possession by Dec 2026 · Nirmiti Realities
Satvam Hills C4
possession by Dec 2026 · Symphony Landmarks LLP
Sparsh Aster
possession by Dec 2026 · Shree Enterprises
Terra Casa - Grande
possession by Dec 2026 · Ambika Realty

Other RERA-registered projects in Pune

Playtor Paud D- Phase 1
declared completion Jun 2023 · Sangam Realty
Playtor Paud D- Phase 2
possession by Sep 2026 · Sangam Realty
Playtor Ranjangaon Midc Phase 4
possession by Apr 2033 · Sujit Santosh Bhansali
Playtor Ranjangaon- Phase 2
declared completion Jun 2022 · Playtor Lifespaces Private Limited
Playtor Ranjangaon- Phase 3
declared completion Dec 2023 · Playtor Lifespaces Private Limited
Pleasure Park
declared completion Dec 2024 · Devadeva Spaces Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026