MahaRERA Property Intelligence · Pune
P52100002910 · Next to Tehsil Office · promoter Sangam Realty
| MahaRERA registration | P52100002910 |
| Registered on | 04 Aug 2017 |
| Promoter-declared completion | 30 Jun 2024 |
| Current status | Certificate Signed |
| Against today | about 25 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Sangam Realty is the promoter of record on 16 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| C2 | 1 | G+7 | 30 Jun 2019 |
| C4 | 1 | G+7 | 30 Jun 2019 |
2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000289968 | 29/12/2023 | POOJA VILAS KULKARNI vs SANGAM REALTY | order passed |
| CC12501234 | 14/04/2025 | ajay ramdas pardeshi vs SANGAM REALTY | order passed |
The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Jun 2024 | 29 Jun 2020 | Due to delay in getting permissions of plinth checking certificate from PMRDA, Pune, we here request you that, we require 1 year extension for completion of our Playtor Paud C - Ph |
| 30 Jun 2024 | 30 Jun 2024 | request for commencement certificate and building material was shortaged |
| 30 Jun 2024 | 31 Dec 2021 | Attached list of Allottes have consented to extend Rera date of completion of the project form 29/12/2020 to 30/09/2022. |
Located at Next to Tehsil Office, Paud-Mulshi Road, Pune City, Pune, 412108. Per the filed land record, the plot is bounded to the north by Remaining Land of Gat No 245, to the south by Adj Forest Property, to the east by Adj C1 Bldg of Phase 1 and to the west by Amenity Space. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 26 km |
| Baner–Balewadi belt | 28 km |
| Pune Junction / city centre | 38 km |
| Magarpatta / Hadapsar IT | 43 km |
| Pune Int'l Airport (Lohegaon) | 44 km |
| Kharadi / EON IT Park | 45 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Playtor Paud C- Phase 2?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Sangam Realty is the promoter on 5 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026