Pune/Project record

MahaRERA · the public record

PMAY AHP MUNCIPAL COUNCIL

INDAPUR · INDAPUR MUNCIPAL COUNCIL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100050165

Delivery and registration

When is the project declared for completion?

PMAY AHP MUNCIPAL COUNCIL is registered with MahaRERA as P52100050165 and the promoter has declared completion for 30 Sep 2025.

30 Sep 2025

declared completion

12months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100050165
Registered on21 Mar 2023
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 12 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PMAY AHP MUNCIPAL COUNCIL record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Indapur Muncipal Council is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In PMAY AHP MUNCIPAL COUNCIL, ₹7.90 Cr of a declared ₹45.94 Cr estimated project cost is reported as incurred, about 17.2%, as at the last certified filing with MahaRERA.

17.2%

₹7.90 Cr

of ₹45.94 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PMAY AHP MUNCIPAL COUNCIL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
B11G+730 Sep 2025
B21G+730 Sep 2025
B31G+730 Sep 2025
B41G+730 Sep 2025
B51G+730 Sep 2025
B61G+730 Sep 2025
SOCIETY OFFICE1G+130 Sep 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at INDAPUR, INDAPUR , Indapur, Pune, 413106. Per the filed land record, the plot is bounded to the north by STATE HIGHWAY ROAD 66, to the south by GAT NO 162, to the east by 9 MTR DP ROAD and to the west by ZP PRIMARY SCHOOL. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Indapur

Raigad City
Not filing quarterly progress reports · possession by Dec 2027 · Bhagavat Dashrath More
Vishwa Residency
possession by Dec 2028 · Not Available
Gods Gift
declared completion May 2026 · Vishal Shivaji Gaikwad
SAI Shrushti
declared completion Dec 2025 · SAI Construction
Vishalata Nisarg
Not filing quarterly progress reports · declared completion Feb 2025 · V. S. Bondre Developers (promoters &
Morya City B
Past its declared completion date · declared completion Oct 2023 · Bhagavat Dashrath More

Other RERA-registered projects in Pune

Pmay- Ravet Sr No. 96 P
declared completion Nov 2022 · Pimpri Chinchwad Municipal Corporation
Pmay Scheme AT Survey NO 89 Part AND 92 Part, Hadapsar, TAL Haveli, Dist Pune
possession by Jun 2027 · Pmay Cell,pune Municipal Corporation
Pmay Scheme AT Survey NO 89 Part AND 92 Part Plot D, Hadapsar, TAL Haveli, Dist Pune
possession by Dec 2026 · Pmay Cell,pune Municipal Corporation
Pmay Scheme AT Survey NO 89 Part AND 92 Part Plot E, Hadapsar, TAL Haveli, Dist Pune
possession by Dec 2026 · Pmay Cell,pune Municipal Corporation
Pmay Scheme AT Survey NO 89 Part AND 92 Part Plot F, Hadapsar, TAL Haveli, Dist Pune
possession by Jun 2027 · Pmay Cell,pune Municipal Corporation
Pmay Scheme Survey NO 57 Hissa NO 5 Part Plot NO 1A OLD Plot NO 1 Kharadi
declared completion Dec 2023 · Pmay Cell,pune Municipal Corporation

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026