MahaRERA Property Intelligence · Pune

POPULAR COLONY

P52100015233 · NEAR RAGHAV DAS VIDYALAYA · promoter Balaji Construction Company

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP52100015233
Registered on08 Feb 2018
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
BUILDING D11G+1231 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201931 May 2020Awating noc from survey of india and certificate for lift, installation of individual meters and noc of drainage and water .
31 Dec 201930 Jun 2021OUR PROJECT IS 100% COMPLETE BUT WE DID NOT GET THE REQUIRED PUNE MUNICIPAL CORPORATION OCCUPATION CERTIFICATE DUE TO COVID 19 SITUATION AND LOCKDOWN. SO WE REQUEST YOU TO CONSIDER

Location, Land & Connectivity

Located at NEAR RAGHAV DAS VIDYALAYA, BACK TO POPULAR NAGAR, Pune City, Pune, 411058. Per the filed land record, the plot is bounded to the north by SURVEY NO 45 PART AND 9M APPROCH ROAD, to the south by SURVEY NO 45 PART, to the east by SURVEY NO -135 and to the west by SURVEY NO 45 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt9 km
Pune Junction / city centre10 km
Hinjewadi Rajiv Gandhi IT Park14 km
Magarpatta / Hadapsar IT14 km
Kharadi / EON IT Park17 km
Pune Int'l Airport (Lohegaon)17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Other RERA-registered projects in Warje

Libero
Not filing quarterly progress reports · possession by Dec 2026 · Satish Bora AND Associates
Ketan Heights Wing / Building No A
possession by Dec 2026 · Ketandevelopers
LE Phoenix
possession by Dec 2026 · Taksh Buildcon
Gulab Shilp
possession by Mar 2027 · Buttepatil Properties
Warje Business Bay
possession by Mar 2027 · Sanvi Developers
Cavansite Phase 2
possession by Jun 2027 · Arma Landmark LLP

Major developers building in Warje

Other RERA-registered projects in Pune

Popular Tower
declared completion Jun 2024 · Popular Promoters AND Developers
Portia
declared completion Dec 2019 · Vilas Javdekar Lifestyle Developers Pvt.
Portia Grande
possession by Dec 2027 · Vilas Javdekar Eco Homes
Power Boulevard
declared completion Dec 2021 · Sapra Properties & Investments
Power Heights AND Power Residences
possession by Dec 2028 · Sapra Constructions
Power Terrace
possession by Mar 2028 · Sapra Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026