Pune/Project record

MahaRERA · the public record

PRIYA APARTMENT

DAUND · M/S Mantri Construction

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100015204

Delivery and registration

When is the project declared for completion?

PRIYA APARTMENT is registered with MahaRERA as P52100015204 and the promoter has declared completion for 30 Sep 2020.

30 Sep 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100015204
Registered on07 Feb 2018
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRIYA APARTMENT record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mantri is the promoter of record on 10 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PRIYA APARTMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
PRIYA APARTMENT1G+531 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DAUND, PATIL CHOWK DAUND DIST PUNE, Daund, Pune, 413801. Per the filed land record, the plot is bounded to the north by RASHIDA N BAGWANS HOUSE ON CTS NO 565A, to the south by 4-5 MTRS WIDE ROAD, to the east by MANTRI HEIGHTS APARTMENT ON CTS 565C 565D and to the west by 4-5 MTRS WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~68 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park68 km
Magarpatta / Hadapsar IT69 km
Pune Int'l Airport (Lohegaon)71 km
Pune Junction / city centre75 km
Baner–Balewadi belt85 km
Hinjewadi Rajiv Gandhi IT Park90 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every M/S Mantri Construction project & its RERA track record →

Other RERA-registered projects in Daund

Shri Ashtavinayak Park
possession by Oct 2026 · Ajay Builders AND Associates Daund
Sai Capital
Not filing quarterly progress reports · possession by May 2027 · Satish Deepak Thorat
R City
possession by Mar 2028 · Reva Construction AND Developers
Shri Govind Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Developers Daund
Shri Hari Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Construction AND Developers Daund
Ekdanta
possession by Dec 2028 · M/S Prakash Construction Co.

Other RERA-registered projects in Pune

Priyadarshan
declared completion Apr 2018 · Gangotree Greenbuild
Priyanjali
possession by Dec 2028 · Madane Constructions
Priyvardhini Bildcon
declared completion Dec 2025 · Priyvardhini Bildcon LLP
PRK Market City
declared completion Dec 2022 · PRK Vhentures
PRK Miracle
possession by Dec 2026 · PRK Realty
Probha Oasis
possession by Jul 2028 · Probha Buildcon Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026