31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100030022

Delivery and registration

When is the project declared for completion?

RAJGAD HEIGHTS is registered with MahaRERA as P52100030022 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100030022
Registered on26 Jul 2021
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJGAD HEIGHTS record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Unique Developers is the promoter of record on 133 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

133projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJGAD HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
RAJGAD HEIGHTS1G+531 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at JALOCHI, BARAMATI JALOCHI ROAD, Baramati, Pune, 413102. Per the filed land record, the plot is bounded to the north by PLOT NO 11, to the south by PLOT NO 8, to the east by GAT NO 162 AND SAYLI HILL COMPOUND WALL and to the west by 9 mt wide road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Unique Developers AND Builders project & its RERA track record →

Other RERA-registered projects in Baramati

Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon
Adarsh Residency
possession by Oct 2026 · Shivshree Developers
Dream City -A Building
possession by Oct 2026 · Tanaji Sadashiv Pansare
Tanai Heights
possession by Nov 2026 · Surekha Vishnu Kumbhar
Tanai G
possession by Nov 2026 · Surekha Vishnu Kumbhar
Shrivishwa Heights
possession by Dec 2026 · Shrivishwa Developers

Other RERA-registered projects in Pune

Rajgruhi Residency Tower C
declared completion Dec 2025 · Wellbuild Merchants Private Limited
Rajgruhi Residency Tower C1
declared completion Dec 2025 · Atria Constructions
Rajhans
possession by May 2027 · Joshi Buildcon Landmarks
Rajkala Dreams
declared completion Dec 2021 · Kavita Rajkumar Patel
Rajkamal Park Co-Op Housing Society Ltd
declared completion Dec 2024 · D & T Properties
Rajlaxmi Prestige
possession by Dec 2029 · Rajlaxmi Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026