Pune/Project record

MahaRERA · the public record

RAM SRUSHTI B

Pune · YOGESH VITTHAL BALWADKAR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013440

Delivery and registration

When is the project declared for completion?

RAM SRUSHTI B is registered with MahaRERA as P52100013440 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013440
Registered on07 Oct 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAM SRUSHTI B record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Yogesh Vitthal Balwadkar is the promoter of record on 7 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAM SRUSHTI B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
B1G+1231 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Haveli, Pune, 411027. Per the filed land record, the plot is bounded to the north by 12 MTR WIDE ROAD, to the south by OPEN SPACE, to the east by CTS NO 778P and to the west by SR NO 19P. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt3 km
Hinjewadi Rajiv Gandhi IT Park5 km
Pune Junction / city centre11 km
Pune Int'l Airport (Lohegaon)14 km
Magarpatta / Hadapsar IT17 km
Kharadi / EON IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimple Nilakh

Sai Neel
possession by Sep 2026 · Vishal Anil Khairnar
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Sai Aura
possession by Sep 2026 · WJV Landmarks LLP
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties
Vimal Twin Tower A Wing
possession by Oct 2026 · Kate Promoters & Developers
Yashoda Heights
possession by Nov 2026 · Paras Shivajirao Dhore

Major developers building in Pimple Nilakh

Other RERA-registered projects in Pune

Rama Ellenza
possession by Dec 2026 · Shyamsundar Ramchandra Kanitkar
Rama Icon
declared completion Dec 2020 · Rama Realtors
Ramaa Heritaige Phase II
possession by Dec 2026 · Grandbay Developers
Ramalay
possession by Dec 2029 · M Square Landmark
Raman Legacy
possession by Dec 2027 · Shree Samarth Developers
Raman Stellar
declared completion Dec 2025 · Soham Shivam Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026