RUDRA DHAM Phase 1

Pune · Rudra Construction & Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

20 Jan 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

20 Jan 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100007588

Delivery and registration

When is the project declared for completion?

RUDRA DHAM Phase 1 is registered with MahaRERA as P52100007588 and the promoter has declared completion for 20 Jan 2021.

20 Jan 2021

declared completion

68months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100007588
Registered on17 Aug 2017
Promoter-declared completion20 Jan 2021
Current statusCertificate Signed
Against todayabout 68 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RUDRA DHAM Phase 1 record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rudra Construction Developers is the promoter of record on 80 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

80projects

registered with MahaRERA

15flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RUDRA DHAM Phase 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Rowhouse A1G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Daund, Pune, 413801. Per the filed land record, the plot is bounded to the north by 15 feet internal road, to the south by Part of Amenity space, to the east by Part of Gat No 89 and to the west by Part of Plot No 3. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~107 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park107 km
Baner–Balewadi belt112 km
Pune Junction / city centre122 km
Pune Int'l Airport (Lohegaon)125 km
Kharadi / EON IT Park128 km
Magarpatta / Hadapsar IT128 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Daund

Shri Ashtavinayak Park
possession by Oct 2026 · Ajay Builders AND Associates Daund
Sai Capital
Not filing quarterly progress reports · possession by May 2027 · Satish Deepak Thorat
R City
possession by Mar 2028 · Reva Construction AND Developers
Shri Govind Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Developers Daund
Shri Hari Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Construction AND Developers Daund
Ekdanta
possession by Dec 2028 · M/S Prakash Construction Co.

Other RERA-registered projects in Pune

Rudra Heritage
possession by Dec 2027 · Rudra Construction
Rudra Palace
declared completion Jul 2020 · Sunil Gajaram Kaware
Rudra Residency
declared completion Dec 2022 · S M Ventures
Rudradeep
declared completion Mar 2026 · Raghvendra Maharudra Tulshibagwale
Rudraksh Home
possession by Dec 2027 · Gurudatta Developers
Rudraksh Vantage
possession by Dec 2027 · Gurudatta Developers

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026