Pune/Project record

MahaRERA · the public record

SAI SIDDHI

DIGHI · S D DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

10 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017813

Delivery and registration

When is the project declared for completion?

SAI SIDDHI is registered with MahaRERA as P52100017813 and the promoter has declared completion for 10 Dec 2020.

10 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017813
Registered on17 Sep 2018
Promoter-declared completion10 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI SIDDHI record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI SIDDHI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
B WING1G+510 Dec 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SAI SIDDHI, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000022834424/02/2023Abhijit Anil Kamble vs DILIP SAHEBRAO GAIKWADpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered10 Dec 2020DUE TO HEAVY RAIN

Location, Land & Connectivity

Located at DIGHI, BHOSARI ROAD, Haveli, Pune, 411015. Per the filed land record, the plot is bounded to the north by 73 PART, to the south by 73 PART, to the east by ROAD and to the west by 73 PART. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhanori

Murli Manohar Heights
possession by Sep 2026 · Padmanabh Associates
Yash Grecia- E Wing
possession by Sep 2026 · Akshay Enterprises
Aaiji Crystal Phase I
possession by Oct 2026 · Aaiji Developers
Aaiji Crystal Phase II
possession by Oct 2026 · Aaiji Developers
Galaxy Co-Operative Housing Society Ltd
possession by Oct 2026 · Yash Developers
Austin
possession by Dec 2026 · Krishna Venture Skyscraper LLP

Major developers building in Dhanori

Other RERA-registered projects in Pune

SAI Siddhi Residency
declared completion Aug 2023 · SAI Siddhi Developers
SAI Signature
possession by Sep 2026 · Shree SAI Creatives
SAI Sneh
declared completion Dec 2024 · Nilesh Dilip Kale
Sai Sneh Phase-I
declared completion Jun 2022 · GS Developers
Sai Solitaire
possession by Nov 2027 · Sankalp Developers
SAI Soukhyam Park
possession by Dec 2029 · Not Available

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026