MahaRERA Property Intelligence · Pune

SAWALI APARTMENTS

P52100032232 · PARVATI · promoter Parmar Realty

Certificate SignedDue 30 May 2024

Delivery & Registration

MahaRERA registrationP52100032232
Registered on15 Dec 2021
Promoter-declared completion30 May 2024
Current statusCertificate Signed
Against todayabout 26 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Parmar Realty is the promoter of record on 17 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SAWALI APARTMENTS1G+630 May 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PARVATI, MITRA MANDAL CO-OP HSG SOCIETY LTD, Pune City, Pune, 411009. Per the filed land record, the plot is bounded to the north by PLOT 62 and 63, to the south by ROAD, to the east by Plot 76 and to the west by PLOT 74. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre4 km
Magarpatta / Hadapsar IT8 km
Baner–Balewadi belt11 km
Kharadi / EON IT Park11 km
Pune Int'l Airport (Lohegaon)12 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Parvati

Hemanti Co-Operative Housing Society
possession by Sep 2026 · Hemanti Sahakari Gruhrachana Sanstha Mar
Serenity Residency
possession by Sep 2026 · Buttepatil Properties
Trimurti
possession by Sep 2026 · Datar Engineering AND Consultancy Privat
Vishwas Apartment
possession by Sep 2026 · Manomay Constructions
Aura
possession by Oct 2026 · Ranjekar & RE-MAP Realty
31 Basil
possession by Dec 2026 · Samarth Builders

Major developers building in Parvati

Other RERA-registered projects in Pune

Sayaji Apartment
possession by Dec 2027 · Sudit Developers
Sayaji Residncy
declared completion Dec 2019 · Sachin Sayaji Bankar
Sayali Complex
declared completion Nov 2019 · Pandit Nanabhau Molak
Sayama Phase 2
possession by Dec 2028 · Puranik Builders Limited
Sayama Phase 3
declared completion Dec 2023 · Puranik Builders Limited
Sayama Phase 4
possession by Dec 2036 · Puranik Builders Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026