Pune/Project record

MahaRERA · the public record

Sharvil

Kondhwa (BK) · Empire Shelters

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100003859

Delivery and registration

When is the project declared for completion?

Sharvil is registered with MahaRERA as P52100003859 and the promoter has declared completion for 30 Nov 2020.

30 Nov 2020

declared completion

70months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100003859
Registered on06 Aug 2017
Promoter-declared completion30 Nov 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sharvil record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Empire Shelters is the promoter of record on 154 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

154projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sharvil in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
A Wing1G+1131 May 2019
B Wing1G+1131 May 2019
C Wing1G+631 May 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 May 2020EVEN AFTER RECEIVING ALL THE REQUIRED NOC BEFORE APPLYING FOR COMPLETION THE NEWLY IMPLEMENTED AIR FORCE NOC IS AWAITED SINCE LONG TIME.

Location, Land & Connectivity

Located at Kondhwa (BK), Katraj Kondhwa Road, Pune City, Pune, 411004. Per the filed land record, the plot is bounded to the north by 66p, to the south by 24 metre Road, to the east by 66p and to the west by 66p. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre5 km
Baner–Balewadi belt6 km
Magarpatta / Hadapsar IT10 km
Pune Int'l Airport (Lohegaon)11 km
Hinjewadi Rajiv Gandhi IT Park12 km
Kharadi / EON IT Park12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Erandwane

Madhumati Chsl
possession by Sep 2026 · Kotibhaskar Infrastructures &develop
Serenity Springs
possession by Sep 2026 · Buttepatil Properties
State Bank OF India Employees Himgauri CO Operative Housing Society LTD
possession by Sep 2026 · Fortune Developers
Swojas Maitree
possession by Sep 2026 · Swojas Enterprises
THE Pleasant CO OP Housing Society LTD
possession by Sep 2026 · Shree Venkatesh Landmarks
Venkatesh Erandwane Central - Building-B1 - Phase 2
possession by Sep 2026 · Shree Venkatesh Buildcon PVT LTD

Major developers building in Erandwane

Other RERA-registered projects in Pune

Shashi Apartments
declared completion Dec 2024 · Chaphalkar Karandikar Developers
Shashitara Hills
declared completion Sep 2022 · Shrikant Shashikant Jagtap
Shashwat
possession by Dec 2027 · Moraya Associates
Shashwat SAI Ratna
possession by Dec 2028 · Shree Sai Ram Properties
Shata Laxmi
declared completion Oct 2020 · Sharad Gangadhar Phapale
Shaurya Residence
declared completion Dec 2024 · 3 S Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026