Pune/Project record

MahaRERA · the public record

Shine City Phase III

Chikhali · Namoh Builders & developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013445

Delivery and registration

When is the project declared for completion?

Shine City Phase III is registered with MahaRERA as P52100013445 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013445
Registered on07 Oct 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shine City Phase III record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Namoh Builders Developers is the promoter of record on 6 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shine City Phase III in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
F Wing1G+1530 Dec 2020
G Wing1G+1531 Dec 2020
D Wing1G+1530 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Delay in obtaining completion certificate due to pandemic

Location, Land & Connectivity

Located at Chikhali , Sonawane wasti, Haveli, Pune, 412114. Per the filed land record, the plot is bounded to the north by E Wing Completed, to the south by Proposed phase, to the east by B and C Wing Completed and Gat Number 1194 and to the west by Gat Number 1197. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park13 km
Baner–Balewadi belt15 km
Pune Int'l Airport (Lohegaon)18 km
Pune Junction / city centre20 km
Kharadi / EON IT Park22 km
Magarpatta / Hadapsar IT24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Namoh Builders & Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Chikhali

Prasanna Paradise
possession by Sep 2026 · Paras Properties
Adhya Radhakrishna C Wing
possession by Oct 2026 · Adhya Properties
Aishwaryam ONE Moshi
possession by Dec 2026 · SAI Essen Developers
Apna Market
possession by Dec 2026 · Universal Developments
Ganesh Paradise Phase 2
Not filing quarterly progress reports · possession by Dec 2026 · Ekdanta Nest LLP
Ganesh Siddhi E Wing
possession by Dec 2026 · Ganeshconstruction

Other RERA-registered projects in Pune

Shirin Harmony
declared completion Dec 2023 · Kshirsagar Builders
Shiv Ganesh Heights
possession by Dec 2028 · Pansare Buildcon
Shiv Harsh Vihar
possession by Dec 2031 · M/S Shiv RAJ Developers
Shiv Heights
declared completion Oct 2021 · Shiv Shakti Developers
Shiv Malhar
declared completion Sep 2018 · Swaraj Developers
Shiv Malhar
possession by Dec 2026 · Shiv Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026