Pune/Project record

MahaRERA · the public record

SHREESAMARTH RESIDENCY

GAT NO 765 CHIKHALI PUNE · DILIP KALURAM MORE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018077

Delivery and registration

When is the project declared for completion?

SHREESAMARTH RESIDENCY is registered with MahaRERA as P52100018077 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018077
Registered on10 Oct 2018
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREESAMARTH RESIDENCY record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dilip Kaluram More is the promoter of record on 9 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREESAMARTH RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SHREE SAMARTH RESIDENCY1G+631 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at GAT NO 765 CHIKHALI PUNE , DEHU ALANDI ROAD, Haveli, Pune, 412114. Per the filed land record, the plot is bounded to the north by PROPERTY OF MR KERU BALGHARE, to the south by PROPERTY OF MR PANDIT BALGHARE, to the east by ROAD and to the west by PROPERTY OF MR ROHIDAS BALGHARE. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chikhali

Prasanna Paradise
possession by Sep 2026 · Paras Properties
Adhya Radhakrishna C Wing
possession by Oct 2026 · Adhya Properties
Aishwaryam ONE Moshi
possession by Dec 2026 · SAI Essen Developers
Apna Market
possession by Dec 2026 · Universal Developments
Ganesh Paradise Phase 2
Not filing quarterly progress reports · possession by Dec 2026 · Ekdanta Nest LLP
Ganesh Siddhi E Wing
possession by Dec 2026 · Ganeshconstruction

Other RERA-registered projects in Pune

Shreesha Icon
possession by Jul 2029 · Imperial Buildcon
Shreetej Apartments
possession by Mar 2027 · Aster Trisha Developers
Shreeya Apartments
declared completion May 2025 · Ranade Bagade Constructions
Shreeya Avenue D Wing
declared completion Jun 2025 · Atul Vinod Bire
Shreeyansh Park
declared completion Jun 2026 · Shriram Developers
Shreeyash
possession by Sep 2028 · Lagoo Apte Properties Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026