Pune/Project record

MahaRERA · the public record

SHRI GANESH PARK PHASE-2

KOLEWADI · SANJAY PARSHURAM KUTE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28units filed as unsoldInventory · 12 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
146registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018052

Delivery and registration

When is the project declared for completion?

SHRI GANESH PARK PHASE-2 is registered with MahaRERA as P52100018052 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018052
Registered on10 Oct 2018
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRI GANESH PARK PHASE-2 record 41 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Sanjay Parshuram Kute is the promoter of record on 15 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

15projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SHRI GANESH PARK PHASE-2, ₹55.15 Cr of a declared ₹83.84 Cr estimated project cost is reported as incurred, about 65.8%, as at the last certified filing with MahaRERA.

65.8%

₹55.15 Cr

of ₹83.84 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SHRI GANESH PARK PHASE-2, 118 of 146 homes filed with MahaRERA are recorded as sold or booked, about 81%, and 28 remain available.

81%sold

118 of 146 homes

₹26.09 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹18.48 Cr (about 71%) is recorded as collected and ₹7.62 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 118 registered agreements, the effective carpet rate is ₹4,106/sqft, with eight in ten falling between ₹3,525 and ₹8,032 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101641 sqft (59.54 sqm)₹3.18 Lakh
Floor 1102631 sqft (58.66 sqm)₹3.13 Lakh
Floor 1103449 sqft (41.75 sqm)₹2.23 Lakh
Floor 1104449 sqft (41.75 sqm)₹2.23 Lakh
Floor 1105631 sqft (58.66 sqm)₹3.13 Lakh
Floor 1106641 sqft (59.54 sqm)₹3.18 Lakh
Floor 2201624 sqft (57.96 sqm)₹3.10 Lakh
Floor 2202625 sqft (58.03 sqm)₹3.10 Lakh
Floor 2203449 sqft (41.75 sqm)₹2.23 Lakh
Floor 2204449 sqft (41.75 sqm)₹2.23 Lakh
Floor 2205625 sqft (58.03 sqm)₹3.10 Lakh
Floor 4402637 sqft (59.18 sqm)₹19.06 Lakh
Ground/Floor 001276 sqft (25.67 sqm)₹1.37 Lakh
Ground/Floor 002310 sqft (28.84 sqm)₹1.54 Lakh
Ground/Floor 003290 sqft (26.98 sqm)₹1.44 Lakh
Ground/Floor 004211 sqft (19.63 sqm)₹1.05 Lakh
Ground/Floor 005211 sqft (19.63 sqm)₹1.05 Lakh
Ground/Floor 006290 sqft (26.98 sqm)₹1.44 Lakh
Ground/Floor 007310 sqft (28.84 sqm)₹1.54 Lakh
Ground/Floor 008276 sqft (25.67 sqm)₹1.37 Lakh
Ground/Floor 009288 sqft (26.78 sqm)₹1.43 Lakh
Ground/Floor 010293 sqft (27.22 sqm)₹1.45 Lakh
Stilt01641 sqft (59.54 sqm)₹3.18 Lakh
Stilt02679 sqft (63.04 sqm)₹3.37 Lakh
Stilt03448 sqft (41.58 sqm)₹2.22 Lakh
Stilt04448 sqft (41.58 sqm)₹2.22 Lakh
Stilt05679 sqft (63.04 sqm)₹3.37 Lakh
Stilt06641 sqft (59.54 sqm)₹3.18 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 118 homes carry one, and 28 of the 146 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
102631 sqftRs 25.44 lakh typical, over Rs 19.23 lakh to Rs 32.85 lakh55 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SHRI GANESH PARK PHASE-2, every one of the 28 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 27 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9 and 146 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
WING A1G+95231 Dec 2024
WING B1G+96631 Dec 2024
WING C1G+92731 Dec 2024
WING D1G+9-31 Dec 2024
COMMERCIAL BUILDING1G+2131 Dec 2024

Unit mix on the filing: 115 residential and 31 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2028DELAY IN OCCUPANCY CERTIFICATE & REVISION IN EXISTING PLAN

Location, Land & Connectivity

Located at KOLEWADI, PUNE, Pune City, Pune, 412110. Per the filed land record, the plot is bounded to the north by EXISTING 15 MT WIDE ROAD, to the south by GHAT NO 1P, to the east by GHAT NO 1P and to the west by EXISTING 12 MT WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre4 km
Magarpatta / Hadapsar IT8 km
Kharadi / EON IT Park11 km
Baner–Balewadi belt11 km
Pune Int'l Airport (Lohegaon)12 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sanjay Parshuram Kute is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Theur

Vintage City Ph 2
possession by Dec 2026 · Eiffel Landmarks Private Limited
MK Estrella
possession by Feb 2027 · Mayra Properties
Unnati Vatika
possession by Apr 2027 · M/S Unnati Lifespace
Nivaan Sparsh Phase-1
possession by Jun 2027 · Not Available
Nivaan Sparsh II
possession by Dec 2027 · Shahaji Sakharam Sawant
Dream City
possession by Jul 2028 · Not Available

Other RERA-registered projects in Pune

Shri Govind Park
possession by Dec 2028 · Ajay Developers Daund
Shri Hari Park
possession by Dec 2028 · Ajay Construction AND Developers Daund
Shri Icon
possession by Dec 2026 · Shri Samarth Buildtech
Shri Keshavlaxmi
possession by Mar 2028 · Amol Ajit Ravetkar
Shri Krishna Oasis
declared completion Jan 2019 · Shri Buildcon
Shri Labsons Apartment
possession by Dec 2026 · Shri Labsons Builders And Developers Pri

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026