Pune/Project record

MahaRERA · the public record

SHRI SWAMI SAMARTH RESIDENCY

DIGHI · M/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

4units filed as unsoldInventory · 18 September 2026
30 Mar 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100034055

Delivery and registration

When is the project declared for completion?

SHRI SWAMI SAMARTH RESIDENCY is registered with MahaRERA as P52100034055 and the promoter has declared completion for 30 Mar 2026.

30 Mar 2026

declared completion

6months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100034055
Registered on17 Mar 2022
Promoter-declared completion30 Mar 2026
Current statusCertificate Signed
Against todayabout 6 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRI SWAMI SAMARTH RESIDENCY record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 43 homes carry one, and 4 of the 47 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
103507 sqftRs 40.70 lakh typical, over Rs 28.75 lakh to Rs 43.00 lakh4 filed on this stack, floors 2–5

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SHRI SWAMI SAMARTH RESIDENCY, every one of the 4 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 3 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
A BUILDING1G+6-
B BUILDING1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2025Due to financial Issue We are not unable to start our construction on site
30 Mar 202530 Mar 2026a) Time taken in Slum TDR loading and procedural compliances with the concerned Departments. b) There is a limited access to the project land. The materials are unloaded away from

Location, Land & Connectivity

Located at DIGHI, DIGHI , Haveli, Pune, 411015. Per the filed land record, the plot is bounded to the north by 18 37 04 1 N 73 52 22 0 E, to the south by 18 37 04 0 N 73 52 23 6 E, to the east by 18 37 03 6 N 73 52 23 5 E and to the west by 18 37 03 7 N 73 52 21 9 E. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)6 km
Pune Junction / city centre10 km
Kharadi / EON IT Park10 km
Baner–Balewadi belt12 km
Magarpatta / Hadapsar IT13 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every M/S Shri Swami Samarth Builders AND Developer project & its RERA track record →

Other RERA-registered projects in Dhanori

Murli Manohar Heights
possession by Sep 2026 · Padmanabh Associates
Yash Grecia- E Wing
possession by Sep 2026 · Akshay Enterprises
Aaiji Crystal Phase I
possession by Oct 2026 · Aaiji Developers
Aaiji Crystal Phase II
possession by Oct 2026 · Aaiji Developers
Galaxy Co-Operative Housing Society Ltd
possession by Oct 2026 · Yash Developers
Austin
possession by Dec 2026 · Krishna Venture Skyscraper LLP

Major developers building in Dhanori

Other RERA-registered projects in Pune

Shri Swaranjali
possession by May 2027 · Amey Shirish Barve
Shri Swararaj
declared completion Dec 2019 · S K Enterprises
Shri Venkatesh Park
declared completion Oct 2025 · Ajay Builders Daund
Shri Vinayak Heights
possession by Mar 2027 · Shri Vinayak Construction
Shri Vishveshwar Apartment
possession by Dec 2028 · Naman Developers
Shridhar Heights
declared completion Mar 2022 · Sachin Vasant Jare

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026