30 Mar 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100027092

Delivery and registration

When is the project declared for completion?

SHRIPAL PARK is registered with MahaRERA as P52100027092 and the promoter has declared completion for 30 Mar 2027.

30 Mar 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100027092
Registered on13 Nov 2020
Promoter-declared completion30 Mar 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRIPAL PARK record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHRIPAL PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SHRIPAL PARK WING B1G+630 Sep 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at OFF MUTHA PETROLEUM, BARAMATI NIRA ROAD, Baramati, Pune, 413115. Per the filed land record, the plot is bounded to the north by GAT NO 661 AND 663, to the south by BARAMATI NIRA ROAD, to the east by GAT NO 683 AND 689 and to the west by REMAINING LAND OF GAT NO 662. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malegaon Bk

Ramraj Residency
possession by Dec 2028 · Ramchandra Dinkar Devkate
Shri Bhavani Market
Not filing quarterly progress reports · possession by Apr 2029 · Shri Bhavani Shankar Developers
Ramraj Residency B Building
possession by Dec 2030 · Ramchandra Dinkar Devkate
Anandwan Apartment
Not filing quarterly progress reports · declared completion Dec 2025 · Rudransh Infra
VNS Nirmaan Infra
Past its declared completion date · declared completion Jul 2023 · VNS Nirmaan Infra
Avadhut Residency Phase II
declared completion Jun 2022 · Yogesh Balasaheb Taware

Other RERA-registered projects in Pune

Shriram Corner
declared completion Dec 2022 · DG Developers
Shriram Corner Phase 2
possession by Dec 2026 · Vision Properties
Shriram Elite
possession by Dec 2030 · Shriram Builders And Developers
Shriram Krupa
declared completion Mar 2025 · M/s.r B Associates
Shriram Park Magic Tower
possession by Dec 2026 · Shakur Musa Hakim
Shriram Pride
declared completion Dec 2021 · Shriram Promiters AND Builders

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026