MahaRERA Property Intelligence · Pune

Shuban Enclave

P52100007474 · Ravet · promoter Sahyadri Devcon

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP52100007474
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sahyadri Devcon is the promoter of record on 42 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~37.4% of the estimated project cost incurred as of the last certificate (₹4.79 Cr spent against a ₹12.80 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. With only ~5 months to the declared date and ~37.4% of the cost incurred, ask the promoter how the balance gets built in the time left.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 44 homes filed with MahaRERA, 9 are sold/booked and 35 remain available (~20% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹5.46 Cr in agreement value so far. Of that, ₹3.80 Cr (~70%) is already collected, ₹1.66 Cr receivable — a read on how far along these sales really are. Note: the project registers 56 homes in total, but this sold/unsold inventory filing covers only 44 of them — the other 12 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 9 registered agreements, the effective carpet rate is ₹8,996/sqft (typical range ₹8,996–₹9,731) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101663 sqft (61.55 sqm)₹39.74 Lakh
Floor 1102663 sqft (61.55 sqm)₹39.74 Lakh
Floor 1102663 sqft (61.55 sqm)₹39.74 Lakh
Floor 1103663 sqft (61.55 sqm)₹39.74 Lakh
Floor 1103663 sqft (61.55 sqm)₹39.74 Lakh
Floor 1104663 sqft (61.55 sqm)₹39.74 Lakh
Floor 2201663 sqft (61.55 sqm)₹39.74 Lakh
Floor 2202663 sqft (61.55 sqm)₹39.74 Lakh
Floor 2202663 sqft (61.55 sqm)₹39.74 Lakh
Floor 2203663 sqft (61.55 sqm)₹39.74 Lakh
Floor 2203663 sqft (61.55 sqm)₹39.74 Lakh
Floor 2204663 sqft (61.55 sqm)₹39.74 Lakh
Floor 2204663 sqft (61.55 sqm)₹39.74 Lakh
Floor 3301663 sqft (61.55 sqm)₹39.74 Lakh
Floor 3302663 sqft (61.55 sqm)₹39.74 Lakh
Floor 3303663 sqft (61.55 sqm)₹39.74 Lakh
Floor 3303663 sqft (61.55 sqm)₹39.74 Lakh
Floor 3304663 sqft (61.55 sqm)₹39.74 Lakh
Floor 3304663 sqft (61.55 sqm)₹39.74 Lakh
Floor 4401663 sqft (61.55 sqm)₹39.74 Lakh
Floor 4402663 sqft (61.55 sqm)₹39.74 Lakh
Floor 4404663 sqft (61.55 sqm)₹39.74 Lakh
Floor 4404663 sqft (61.55 sqm)₹39.74 Lakh
Floor 5503663 sqft (61.55 sqm)₹39.74 Lakh
Floor 5504663 sqft (61.55 sqm)₹39.74 Lakh
Floor 6603663 sqft (61.55 sqm)₹39.74 Lakh
Floor 6604663 sqft (61.55 sqm)₹39.74 Lakh
Floor 6604663 sqft (61.55 sqm)₹39.74 Lakh
Floor 7701663 sqft (61.55 sqm)₹39.74 Lakh
Floor 7702663 sqft (61.55 sqm)₹39.74 Lakh
Floor 7702663 sqft (61.55 sqm)₹39.74 Lakh
Floor 7703663 sqft (61.55 sqm)₹39.74 Lakh
Floor 7703663 sqft (61.55 sqm)₹39.74 Lakh
Floor 7704663 sqft (61.55 sqm)₹39.74 Lakh
Floor 7704663 sqft (61.55 sqm)₹39.74 Lakh

⚠ The inventory filing also declares: 12 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 56 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Shuban enclave Wing D1G+82801 Dec 2020
SHUBAN ENCLAVE Wing E1G+82801 Dec 2020
SHUBAN ENCLAVE1--01 Dec 2020

Unit mix on the filing: 56 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
01 Dec 202031 Dec 2026Earlier, we had plan to develop the residential building in survey number 110/1 of Ravet, the plans were sanctioned by the authority Pimpri Chinchwad municipal corporation but due

Location, Land & Connectivity

Located at Ravet, Maharashtra, Haveli, Pune, 411044. Per the filed land record, the plot is bounded to the north by Survey No 110 1, to the south by Survey No 110 1 and 109 2, to the east by Survey No 110 1 and to the west by Survey No 109 2. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park7 km
Baner–Balewadi belt11 km
Pune Junction / city centre20 km
Pune Int'l Airport (Lohegaon)20 km
Kharadi / EON IT Park24 km
Magarpatta / Hadapsar IT25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nigdi

Swastik Platinum
possession by Jul 2026 · Swastik Infinity
THE Saga
possession by Sep 2026 · Nest Saswad Realty LLP
Aashirwad Homes
possession by Dec 2026 · Nest Saswad Realty LLP
Paradise Residency
possession by Dec 2026 · Balaji Developers
Vision Vanessa
possession by Dec 2026 · P4 Group
Swastik Vyom
possession by Mar 2027 · Swastik Venture

Other RERA-registered projects in Pune

Shubh Aangan
declared completion Jun 2023 · Creative Properties
Shubh Aarambh
declared completion Jun 2023 · Siddhivinayak Developers
Shubh Aarambh
declared completion Mar 2024 · Shubh Associates
Shubh Elara
possession by Dec 2028 · Shubhmatoshri Associates LLP
Shubh Evan A1 Wing
declared completion Dec 2023 · Shubh Enterprises
Shubh Evan B1 Wing
declared completion Dec 2024 · Shubh Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026