Pune/Project record

MahaRERA · the public record

SIDDHARTH HEIGHTS

WANAWADI · VARDAN DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100024210

Delivery and registration

When is the project declared for completion?

SIDDHARTH HEIGHTS is registered with MahaRERA as P52100024210 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100024210
Registered on27 Jan 2020
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIDDHARTH HEIGHTS record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vardan Developers is the promoter of record on 8 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIDDHARTH HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
VARDAN HEIGHTS A WING1G+331 Dec 2023
VARDAN HEIGHTS B WING1G+331 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at WANAWADI, -, Haveli, Pune, 411040. Per the filed land record, the plot is bounded to the north by 40FT ROAD THROUGH FOREST LAND, to the south by SURVEY NUMBER 57 PART, to the east by GOVERNMENT FOREST LAND and to the west by REMAINING LAND OF S NO 57. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wanawadi

Gold Crest
possession by Dec 2026 · Golden Magnum
Mainland Eternia
possession by Dec 2026 · Mainland Spaces LLP
Revanta
possession by Dec 2026 · Surana Landmarks LLP
The Deva Residences
possession by Dec 2026 · Suresh Devendra Kothari HUF
Ram Residency
possession by Jan 2027 · Opulent Builders
Ishanand
possession by Jun 2027 · Makawana Bros & CO

Other RERA-registered projects in Pune

Siddhesh Gauri
possession by May 2029 · Siddhesh Developers Unit-2
Siddhesh Shreeram
declared completion Aug 2025 · Siddhesh Developers
Siddhesh - Yashoda
possession by Oct 2027 · Siddhesh Developers Unit - 1
Siddheshwar Apartment
possession by Dec 2028 · Rajesh Chandrakant Shah
Siddheshwar Residency Park Phase I
declared completion Dec 2025 · Rajendra Murlidhar Godbole
Siddhi Ananta
possession by Jul 2027 · Siddhivinayak Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026