SIGNIX

NEAR RAJARAM BRIDGE, PARVATI · CHOULWAR ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100034713

Delivery and registration

When is the project declared for completion?

SIGNIX is registered with MahaRERA as P52100034713 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100034713
Registered on20 Apr 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIGNIX record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Choulwar Associates is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIGNIX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SIGNIX1G+831 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NEAR RAJARAM BRIDGE, PARVATI, SINHAGAD ROAD, Pune City, Pune, 411052. Per the filed land record, the plot is bounded to the north by CANAL, to the south by 45 M W DP ROAD, to the east by FP NO 540-1 and to the west by FP NO 540-3. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karvenagar

Ganga Lahari CO-Operative Housing Society LTD
possession by Oct 2026 · M/S Gokhale Constructions
Gomati Narmada Chsl
possession by Dec 2026 · Kotibhaskar Infrastructures &develop
LE Skylark
possession by Dec 2026 · Kakade Green Estates Private Limited
Anika Gokul Niwas
possession by Dec 2026 · Not Available
Ekdant
possession by Dec 2026 · Swojas Icon Associates LLP
Saukhyam
possession by Apr 2027 · Ranjekar Sahasrabudhe LLP

Other RERA-registered projects in Pune

Signum
declared completion Nov 2023 · Pride Realty
Sikandar Apartments
declared completion Aug 2023 · Radhika Developers
Silicon BAY Phase I
declared completion Dec 2019 · Karan Janhavi Development Coroporation
Silicon BAY Phase III
declared completion Jul 2024 · Karan Janhavi Development Coroporation
Silvan Canopy
possession by Dec 2028 · Soham Associates
Silvenia
declared completion Jun 2026 · Associated Recons LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026