Pune/Project record

MahaRERA · the public record

SRINIVASA

PIRANGUT HINJEWADI · LAXMI HEMANT CHAVAN

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100015587

Delivery and registration

When is the project declared for completion?

SRINIVASA is registered with MahaRERA as P52100015587 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100015587
Registered on08 Mar 2018
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SRINIVASA record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Laxmi Hemant Chavan is the promoter of record on 65 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

65projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SRINIVASA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
SRINIVASA1G+930 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021Due to COVID - 19 issues we faced lot of material and labour availability issues which resulted in delay in completing project. In spite of all odds we managed to complete 90 % of
30 Jun 202131 Dec 2021Respected Authority, Due to COVID - 19 second wave our site was total closed for 5 months as per government orders ( our area was in RED Zone ). Now government authorities have a
31 Dec 202131 Dec 2023Project is under completion - File submitted for completion

Location, Land & Connectivity

Located at PIRANGUT HINJEWADI, SURVEY NO 91 / 1 / B, SRINIVASA, KRUSHNA NAGAR, AMBADVET, Haveli, Pune, 412108. Per the filed land record, the plot is bounded to the north by PART OF SURVEY NO 91, to the south by PART OF SURVEY NO 91, to the east by 40 FEET PRIVATE ROAD AND PIRANGUT HINJEWADI ROAD and to the west by PART OF SURVEY NO 91. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park26 km
Baner–Balewadi belt28 km
Pune Junction / city centre38 km
Magarpatta / Hadapsar IT43 km
Pune Int'l Airport (Lohegaon)44 km
Kharadi / EON IT Park45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Paud

Playtor Paud D- Phase 2
Deregistered by MahaRERA · possession by Sep 2026 · Sangam Realty
Shivangan
possession by Nov 2026 · R M Developers Pune
Nishigandh, B Wing
possession by Dec 2026 · Nirmiti Realities
Satvam Hills C4
possession by Dec 2026 · Symphony Landmarks LLP
Sparsh Aster
possession by Dec 2026 · Shree Enterprises
Terra Casa - Grande
possession by Dec 2026 · Ambika Realty

Other RERA-registered projects in Pune

SRK Gold
possession by Mar 2028 · M/S SRK Constructions
Srushti Apartment
declared completion Jan 2020 · Rachana Creaters
Stalwart Business Enclave
possession by Dec 2028 · Kiran Creators And Developers Private Li
Star Altair Phase II
possession by Dec 2026 · Aryavart Associates
Star Gold Properties
possession by Dec 2028 · Perfect Builders
Star Max
declared completion Dec 2022 · Tingre Agarwal Developer

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026