31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100000302

Delivery and registration

When is the project declared for completion?

Sun Aura is registered with MahaRERA as P52100000302 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100000302
Registered on15 Jul 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sun Aura record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mittal Vastushilp Llp is the promoter of record on 24 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

24projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sun Aura in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Wing A1G+431 Dec 2018
Wing B1G+431 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Sr Div Reddy Court5082004Stayed By Hon High Court

Location, Land & Connectivity

Located at Anand Nagar, Sun City Road, Pune City, Pune, 411051. Per the filed land record, the plot is bounded to the north by S No 8-1and2 and 8 - 3, to the south by S No 7, to the east by S No 8 - 11 and to the west by S No 8-9. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre9 km
Baner–Balewadi belt11 km
Magarpatta / Hadapsar IT13 km
Kharadi / EON IT Park16 km
Hinjewadi Rajiv Gandhi IT Park16 km
Pune Int'l Airport (Lohegaon)17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mittal Vastushilp LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Dhayari

Sai Ganesh Vihar D Wing
possession by Nov 2026 · Jayshree Developers
Aura Waters Phase -I
possession by Dec 2026 · Ranawat Properties
Kanchan Heights
possession by Apr 2027 · Orbiz Estate
Venkatesh Skydale Phase 4
possession by Jun 2027 · Shree Venkatesh Buildcon
Park Life Wing C
possession by Mar 2028 · Kudale Patil AND Jadhav Ventures
Aura Waters Phase II
possession by Dec 2029 · Ranawat Properties

Other RERA-registered projects in Pune

Sun City - Ambegaon Phase - III
declared completion Mar 2026 · Mittal Projects
Sun Emerald
possession by Dec 2029 · Jindal Mittal Graha Nirman Pvt. Ltd.
SUN Garnet
possession by Dec 2030 · Jindal Mittal Graha Nirman Pvt. Ltd.
SUN Glory
possession by Mar 2031 · Jindal Mittal Graha Nirman Pvt. Ltd.
Sun Orchid
possession by Jun 2027 · Mittal Projects
Sun Platina
possession by Mar 2030 · Jindal Mittal Graha Nirman Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026