MahaRERA Property Intelligence · Pune

Supurti

P52100026311 · NORTH PARVATI · promoter Creative Developers

Certificate SignedDue 25 Jun 2024

Delivery & Registration

MahaRERA registrationP52100026311
Registered on07 Sep 2020
Promoter-declared completion25 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Creative Developers is the promoter of record on 49 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SUPURTI1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202331 Mar 2024Sir We are in process of taking Fire NOC from respective authority, the same may take time of around 2 month which by end of October 2023, We will get Fire NOC after that I can su
30 Sep 202325 Jun 2024Your honor, since our first extended date of completion of the project is 31.03.2024. There are total 35 flats out of which 34 flat are ready to handover/complete as per our first

Location, Land & Connectivity

Located at NORTH PARVATI, SINHGAD ROAD, Haveli, Pune, 411009. Per the filed land record, the plot is bounded to the north by BY PLOT NO 7 OF LAYOUT, to the south by BY OPEN SPACE OF ENTIRE LAYOUT, to the east by PROPERTY OWNED BY MR SHENDKAR and to the west by BY ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Parvati

Hemanti Co-Operative Housing Society
possession by Sep 2026 · Hemanti Sahakari Gruhrachana Sanstha Mar
Serenity Residency
possession by Sep 2026 · Buttepatil Properties
Trimurti
possession by Sep 2026 · Datar Engineering AND Consultancy Privat
Vishwas Apartment
possession by Sep 2026 · Manomay Constructions
Aura
possession by Oct 2026 · Ranjekar & RE-MAP Realty
31 Basil
possession by Dec 2026 · Samarth Builders

Major developers building in Parvati

Other RERA-registered projects in Pune

Sur At Nanded City
declared completion Aug 2025 · Nanded City Development & Constructi
Surabhi
declared completion Dec 2023 · Pandit Javdekar Associates
Surabhi City Phase 1
possession by Dec 2030 · Surabhi Group
Surabhi Garden
declared completion Dec 2021 · Surabhi Developers
Surabhi Heights
declared completion Mar 2022 · Maharashtra Developers
Surabhi Iconica
declared completion Dec 2023 · Surabhi Ventures

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026