Pune/Project record

MahaRERA · the public record

SURAJYA PHASE 1

VILLAGE DONAJE · BALARK BUILDCON

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100034951

Delivery and registration

When is the project declared for completion?

SURAJYA PHASE 1 is registered with MahaRERA as P52100034951 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100034951
Registered on28 Apr 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SURAJYA PHASE 1 record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In SURAJYA PHASE 1, 0 of 25 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 25 remain available.

0%sold

0 of 25 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SURAJYA PHASE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SURAJYA PHASE 1, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1240020924/09/2024LALIT MOTILAL BAFNA HUF vs BALARK BUILDCONorder passed

Location, Land & Connectivity

Located at VILLAGE DONAJE , GAT NO. 430, 431, 433 (P), Pune City, Pune, 411025. Per the filed land record, the plot is bounded to the north by BOUNDRY OF GORHE BK, to the south by 60 METER STATE HIGHWAY, to the east by GAT NO 433 HISSA 1 PART and to the west by NALAH. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Gorhe Bk

OM Tapovan
possession by Dec 2026 · OM Tapovan
Panna Niwas
possession by Dec 2026 · Unique Developers
Vrundavan
possession by Jun 2027 · SAI Ganesh Associates
Mindspace Villas Phase I
possession by Dec 2028 · MS Lifestyle Resorts
Pakhar 2 AND 3 BHK Nests
possession by Dec 2028 · Royal Developers AND Builders
The Back Water Residency Phase II - B Building
Deregistered by MahaRERA · declared completion Dec 2025 · LNK Projects Through Proprietor Mr Naray

Other RERA-registered projects in Pune

Surashree
declared completion Dec 2025 · Shlok-Karan Associates
Suratwala Mark Plazzo- Building C, D AND E
possession by Dec 2027 · Suratwwala Business Group Limited
Surbhi Samrudhi
declared completion Jun 2026 · Prakriti Space LLP
Surobhi Elite
possession by Jul 2027 · Ssrpl Pune LLP
Surobhi Regency
possession by Jul 2027 · Ssrpl Pune LLP
Suruddhi Heights
possession by May 2027 · SNS Landmark Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.