SUYOG SAMRAJYA

NARAYANGAON · ASHIRWAD INFRASTRUCTURES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

279units filed as unsoldInventory · 12 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
279registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100076678

Delivery and registration

When is the project declared for completion?

SUYOG SAMRAJYA is registered with MahaRERA as P52100076678 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100076678
Registered on20 Jun 2024
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUYOG SAMRAJYA record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Ashirwad Infrastructures is the promoter of record on 32 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

32projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In SUYOG SAMRAJYA, 0 of 279 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 279 remain available.

0%sold

0 of 279 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SUYOG SAMRAJYA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 September 2026

What the filings record, home by home

Read from MahaRERA on 12 September 2026

No home in SUYOG SAMRAJYA carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 279 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 3,188 a sq ft typical, over Rs 1,354 to Rs 5,295.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 279 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 279 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 279 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SUYOG SAMRAJYA1G+627931 Dec 2027

Unit mix on the filing: 109 residential and 170 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NARAYANGAON, NARAYANGAON, Junnar, Pune, 410504. Per the filed land record, the plot is bounded to the north by SURESH VARHADI PROPERTY, to the south by SHRINIWAS ASSOCIATES PROPERTY, to the east by PUNE NASHIK ROAD and to the west by GMRT COMPOUND. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8293 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park8293 km
Baner–Balewadi belt8296 km
Pune Junction / city centre8306 km
Magarpatta / Hadapsar IT8312 km
Pune Int'l Airport (Lohegaon)8312 km
Kharadi / EON IT Park8313 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Narayangaon

Crystal Tower
possession by Dec 2026 · Jadhav Civil Project
Divyata Park
possession by Dec 2026 · Shantaram J Gadhve
Vizion Galaxy D
possession by Dec 2026 · Vizion Construction
Landmark Paradise
possession by Jul 2027 · Landmark Promoters & Builders
Prime Vastu
possession by Jul 2027 · Prime Construction
Gaurinandan Heights
possession by Dec 2027 · Trident Civil Projects

Other RERA-registered projects in Pune

Suyog Shrushti
possession by Dec 2028 · Suyog Anjani Avishkar Buildcon
Suyog Siyona
possession by Dec 2026 · Sanjay Suresh Jain
Suyog Space - Phase I
declared completion Dec 2022 · Suyog Builders
Suyog Space - Phase II
declared completion Dec 2025 · Suyog Builders
Suyog Srivatsa
possession by Dec 2028 · Shivalay Properties
Suyog Sweet Home
possession by Mar 2027 · Suyog Development Corporation Pune LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026