Pune/Project record

MahaRERA · the public record

Swapna Shilpa Appartment

Kasarwadi, Pune · Santosh Arun Kaspate

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100030841

Delivery and registration

When is the project declared for completion?

Swapna Shilpa Appartment is registered with MahaRERA as P52100030841 and the promoter has declared completion for 30 Nov 2024.

30 Nov 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100030841
Registered on20 Sep 2021
Promoter-declared completion30 Nov 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Swapna Shilpa Appartment record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Santosh Arun Kaspate is the promoter of record on 127 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

127projects

registered with MahaRERA

23flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Swapna Shilpa Appartment in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A Wing1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Nov 2024We request you to Extend the Proposed Date of Completion to 30/11/2024 due to delay in Executing the Project on account of substantial increase in cost and change in Plans at exist

Location, Land & Connectivity

Located at Kasarwadi, Pune, Survey No 419/1, Haveli, Pune, 411034. Per the filed land record, the plot is bounded to the north by DP Road, to the south by DP Road and Government School, to the east by Vishal Chaitanya Hsg Society and to the west by Property of Ram Pimple. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kasarwadi

Unity Park
possession by Dec 2026 · Shriram Vision
Vishal Complex E Wing
possession by Mar 2027 · Vishal Chordiya Constructions Private Li
Square 9
possession by Jun 2027 · Skyline Builders & Developers
Chaitanya Apartments
possession by Dec 2027 · Vishwatmak Realtors LLP
Parshwa Green Edge
possession by Aug 2028 · Shreyas Ashokkumar Pagariya
Mathura Vaibhav
possession by Dec 2028 · Lande Patil Associates

Major developers building in Kasarwadi

Other RERA-registered projects in Pune

Swapnakunj Residency
declared completion Jun 2026 · Capetown Properties
Swapnali CO OP HSG SOC
declared completion Jun 2025 · Vyas Buildcon Pvt. Ltd.
Swapnalok Developers, Swapnalok Nagari Bhor,- Plots -Phase 2
declared completion Dec 2024 · Swapnalok Developers
Swapnalok Nagari, Bhor, Building NO. 4
possession by Dec 2027 · Swapnalok Developers
Swapnalok Nagari Plots
declared completion Mar 2019 · Swapnalok Developers
Swapnalok Phase II
declared completion Dec 2022 · Manav Krushnai Developers Through Its Pr

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026