Pune/Project record

MahaRERA · the public record

SWAROOP HOMES

Pune · SWAROOP HOMES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

20 Nov 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

20 Nov 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013909

Delivery and registration

When is the project declared for completion?

SWAROOP HOMES is registered with MahaRERA as P52100013909 and the promoter has declared completion for 20 Nov 2026.

20 Nov 2026

declared completion

2months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013909
Registered on02 Nov 2017
Promoter-declared completion20 Nov 2026
Current statusCertificate Signed
Against today2 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SWAROOP HOMES record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Swaroop Homes Llp is the promoter of record on 32 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

32projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SWAROOP HOMES in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Plot No 7 and 81--
WING A1G+13-
WING B1G+13-
WING D1G+13-
WING E1G+13-
WING C1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court1261/20162016Pending

Location, Land & Connectivity

Located at Pune City, Pune, 411062. Per the filed land record, the plot is bounded to the north by 12 M WIDE ROAD OF LAYOUT, to the south by PLOT NO 1 OF LAYOUT, to the east by PLOT NO 9 SURVEY NO 94 P and to the west by 12 M WIDE ROAD OF LAYOUT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~117 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park117 km
Baner–Balewadi belt123 km
Pune Junction / city centre133 km
Pune Int'l Airport (Lohegaon)134 km
Kharadi / EON IT Park137 km
Magarpatta / Hadapsar IT138 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chikhali

Elite 28
possession by Sep 2026 · Anita Mahadev Giri
Parshwa Solitaire
possession by Sep 2026 · Parshwa Realtors
North East Business Centre
possession by Nov 2026 · Shiv Properties
Vijay Residency
possession by Dec 2026 · Rudra Infra
Akashvedh Phase 2
possession by Dec 2026 · Raghvendra Buildcon
Bhumi Silveriio Phase 3
possession by Dec 2026 · Bhumi Shelters Private Limited

Other RERA-registered projects in Pune

Swarupnalini
declared completion Dec 2024 · Nestcon
Swastik Dreams
declared completion Sep 2020 · Dhananjay Damodhar Darekar
Swastik Homes
declared completion Mar 2025 · Prestige Infracon
Swastik Iris
declared completion Jun 2022 · Swastik Infra
Swastik Madhav
declared completion Jun 2020 · Swastik Infra
Swastik Magnus
declared completion Dec 2021 · Swastikconstruction

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026