SWAYAMPRABHA

Rambaug Colony · Gruha Navnirman Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 Aug 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 Aug 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100001118

Delivery and registration

When is the project declared for completion?

SWAYAMPRABHA is registered with MahaRERA as P52100001118 and the promoter has declared completion for 15 Aug 2019.

15 Aug 2019

declared completion

85months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100001118
Registered on26 Jul 2017
Promoter-declared completion15 Aug 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SWAYAMPRABHA record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Gruha Navnirman Developers is the promoter of record on 24 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

24projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SWAYAMPRABHA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
SWAYAMPRBHA1G+10-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered15 Aug 2019We hereby request for extension again due to following reasons. Part Completion was received from PMC on date 16/05/2018 Due to various compliance related issues at society end a
15 Aug 201915 Aug 2019We hereby request for extension of 4 months in order to finish the site which is more than 80% complete. Kindly find below few major reasons for delay: 1. The last commencement

Location, Land & Connectivity

Located at Rambaug Colony, Rambaug Colony, Pune City, Pune, 411030. Per the filed land record, the plot is bounded to the north by PMC ROAD, to the south by PLOT NO 13, to the east by PLOT NO 30 and to the west by PLOT NO 28. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre3 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park10 km
Baner–Balewadi belt11 km
Pune Int'l Airport (Lohegaon)11 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Gruha Navnirman Developers is the promoter on 5 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Gruha Navnirman Developers

Gruha Navnirman Developers
Past its declared completion datePune

Other RERA-registered projects in Sadashiv Peth

Krishna Kamal
possession by Sep 2026 · Vakratund Reality
Rukmini Niwas
possession by Sep 2026 · R. B. Chaphalkar Homes Pvt. Ltd.
SAI - Lalitha
possession by Dec 2026 · Sairam Developers
9 Sadashiv C Building
possession by Dec 2026 · Pinnacle Neostar Corporation Pvt. Ltd.
Sadashiv Vishnu
Not filing quarterly progress reports · possession by Dec 2026 · Sadashiv Vishnu Realty LLP
Enjays Paramount
possession by Dec 2026 · Enjay Infra

Major developers building in Sadashiv Peth

Other RERA-registered projects in Pune

Sweet Home CO-Operative Housing Society
possession by Mar 2027 · Ashwamedh Spaces Private Limited
Sweet Home Pmay
declared completion May 2025 · Deshmukh Developments
Swiss Plaza
declared completion Mar 2019 · Moti Udharam Panjabi
Swojas Aasara
possession by Sep 2028 · Swojas United Constructions LLP
Swojas Advait
declared completion Apr 2026 · Swojas Realtors LLP
Swojas Avani
declared completion Jun 2025 · Swojas Realtors LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.