MahaRERA Property Intelligence · Pune

TCG PANORAMA PHASE-II BLDG - B

P52100001924 · AMBEGAON B · promoter The Construction Development

Certificate SignedDue 30 Jan 2023

Delivery & Registration

MahaRERA registrationP52100001924
Registered on29 Jul 2017
Promoter-declared completion30 Jan 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, The Construction Development is the promoter of record on 6 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
TCG PANORAMA PHASE-II BLDG - B1G+1430 Jan 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at AMBEGAON B, KATRAJ AMBEGAON ROAD, Pune City, Pune, 411046. Per the filed land record, the plot is bounded to the north by 12 MTR WIDE SERVICE ROAD , to the south by PHASE I BLDG - C , to the east by PHASE III BLDG - A and to the west by EXISTING 7500 MM ROAD PROPOSED 9 MTR WIDE ROAD . Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre9 km
Magarpatta / Hadapsar IT11 km
Baner–Balewadi belt13 km
Kharadi / EON IT Park15 km
Pune Int'l Airport (Lohegaon)17 km
Hinjewadi Rajiv Gandhi IT Park19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

THE Construction & Development Company is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every THE Construction & Development Company project & its RERA track record →

Other flagged projects by THE Construction & Development Company

THE Construction & Development Company
FlaggedPune
THE Construction & Development Company
FlaggedPune
THE Construction & Development Company
FlaggedPune
THE Construction & Development Company
FlaggedPune

Other RERA-registered projects in Katraj

Aishwarya Heights
possession by Jul 2026 · Shree Sadguru Construction
Basil Chandrakant
possession by Jul 2026 · Shree Sadguru Developers
Vastushree Phase-1
possession by Aug 2026 · Vastu Construction
Capella
possession by Aug 2026 · D K Realties
Divya Elite
possession by Aug 2026 · RRS Infracon LLP
Yogamrut
Not filing quarterly progress reports · possession by Aug 2026 · Jay Ganesh Buildcon

Major developers building in Katraj

Other RERA-registered projects in Pune

Tech Tower
possession by Dec 2028 · Raisoni Properties
Teerth Avila
declared completion Dec 2024 · Vijay Tukaram Raundal
Teerth Technospac 10
declared completion Dec 2019 · Teerth Developers AND Teerth Realties JV
Teerth Technospace 1
declared completion Dec 2019 · Teerth Developers AND Teerth Realties JV
Teerth Technospace 11
declared completion Dec 2019 · Teerth Developers AND Teerth Realties JV
Teerth Technospace 12
declared completion Dec 2019 · Teerth Developers AND Teerth Realties JV

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026