The Beverly Hills

Kunenama · GG Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018166

Delivery and registration

When is the project declared for completion?

The Beverly Hills is registered with MahaRERA as P52100018166 and the promoter has declared completion for 30 Nov 2019.

30 Nov 2019

declared completion

82months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018166
Registered on11 Oct 2018
Promoter-declared completion30 Nov 2019
Current statusCertificate Signed
Against todayabout 82 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for The Beverly Hills record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for The Beverly Hills in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
The Beverly Hills1G+130 Nov 2019
The Beverly Hills1G+130 Nov 2019
The Beverly Hills1G+130 Nov 2019
The Beverly Hills1G+130 Nov 2019

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for The Beverly Hills, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000006440217/07/2020Jeetendra Keshin Gehi vs GG Developersorder passed
CC00500000006469101/10/2020Mahesh Mothreja vs GG Developersorder passed

Location, Land & Connectivity

Located at Kunenama, Kune, Mawal, Pune, 410301. Per the filed land record, the plot is bounded to the north by road, to the south by Survey No 81, to the east by Survey no 85 and to the west by Amenities space. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

GG Developers is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by GG Developers

GG Developers
Past its declared completion datePune

Other RERA-registered projects in Taluka Maval

Olympiadorous Phase I
possession by Feb 2027 · Neel Buildcon

Other RERA-registered projects in Pune

THE Bhanpurawalas
possession by Dec 2028 · THE Bhanpurawalas
THE Business Gate
possession by Oct 2026 · Kesar Vasudev Properties
The Business Hive
declared completion Jan 2021 · M/s. Life Properties
THE Butterfly
possession by Jul 2027 · Vishwa Developers
The Camelia Phase - 1
possession by Jan 2027 · Akanksha Builders
The Canary Phase 2
possession by Dec 2027 · Grow India Nirmiti LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026