Pune/Project record

MahaRERA · the public record

Varadshree

Parvati · VARADSHREE CO-OP HSG SOCIETY LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2028declared completionMahaRERA registration · read 10 Sep 2026
10registered unitsMahaRERA registration · read 10 Sep 2026
Certificate Signedregistration statusMahaRERA registration · read 10 Sep 2026

The record · free to read

Registration read 10 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 10 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1260002601159

Delivery and registration

When is the project declared for completion?

Varadshree is registered with MahaRERA as PR1260002601159 and the promoter has declared completion for 31 Jul 2028.

31 Jul 2028

declared completion

22months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 10 Sep 2026

MahaRERA registrationPR1260002601159
Registered on14 Jul 2026
Promoter-declared completion31 Jul 2028
Current statusCertificate Signed
Against today22 months to the declared date

Sales

How much has actually been sold?

In Varadshree, 0 of 3 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 3 remain available.

0%sold

0 of 3 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 10 homes in total, while this sold/unsold inventory filing covers 3 of them.

Source · MahaRERA sold/unsold inventory filing · read 10 Sep 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 22011,450 sqft (134.67 sqm)₹1.70 Cr
Floor 6601951 sqft (88.38 sqm)₹1.11 Cr
Floor 7702951 sqft (88.38 sqm)₹1.11 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Varadshree in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 10 Sep 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 10 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Varadshree CHS1G+710-

Unit mix on the filing: 10 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2028NA

Location, Land & Connectivity

Located at Parvati, CTS 1217 plot no 45 Tulshibaugwale colony Sahakarnagar, Haveli, Pune, 411009. Per the filed land record, the plot is bounded to the north by Plot No.46, to the south by Plot No.44, to the east by By Lane No 04 and to the west by Plot No. 42. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre5 km
Magarpatta / Hadapsar IT9 km
Baner–Balewadi belt11 km
Kharadi / EON IT Park12 km
Pune Int'l Airport (Lohegaon)13 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Parvati

Serenity Residency
possession by Sep 2026 · Buttepatil Properties
Trimurti
possession by Sep 2026 · Datar Engineering AND Consultancy Privat
Vishwas Apartment
possession by Sep 2026 · Manomay Constructions
Arco Skylife
possession by Dec 2026 · Arco Engineers
Moreshwar Enclave
possession by Dec 2026 · Moreshwar Developers
Shantanu Height
possession by Dec 2026 · Shashidhar Singh

Other RERA-registered projects in Pune

Varadsiddhi Plaza
declared completion Jun 2026 · Varadsiddhi Associates
Varda Galaxy
possession by Dec 2028 · Yashada Developers
Vardhaman Altezza
possession by Jun 2028 · Shree Vardhaman Associates
Vardhaman Dreams Phase II
declared completion Dec 2019 · Vardhman Propertise
Vardhaman Heights
possession by Dec 2029 · Vardhaman Developers
Vardhaman Residency
declared completion Jun 2019 · Vardhaman Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026