MahaRERA Property Intelligence · Pune

VED VIHAR

P52100011964 · promoter Prakash Bhondwe

Certificate SignedDue 31 Dec 2022

Delivery & Registration

MahaRERA registrationP52100011964
Registered on01 Sep 2017
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
VED VIHAR1G+1030 Jun 2022
SAMVED1-30 Jun 2022
BHALCHANDRA1-30 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202231 Dec 2022Delay in receiving completion. We are in process of completing formalities.
31 Dec 202231 Dec 2021Below are the reasons for project falling behind schedule: 1.Lack of funds: The main reason behind lack of funds is inadequate number of bookings.Whatever is constructed on site

Location, Land & Connectivity

Located at Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by 147, to the south by 147, to the east by 180 and to the west by 149. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~117 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park117 km
Baner–Balewadi belt123 km
Pune Junction / city centre133 km
Pune Int'l Airport (Lohegaon)134 km
Kharadi / EON IT Park137 km
Magarpatta / Hadapsar IT138 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ravet

Shivratna
possession by Jul 2026 · Mr Rajan Vishram Palekar
Glorious Tathastu
possession by Jul 2026 · Glorious Buildcon
Aqua Life
possession by Aug 2026 · Legacy Lifespaces LLP
City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited

Major developers building in Ravet

Other RERA-registered projects in Pune

VED Vihar Phase II - Building NO. 4
declared completion Jan 2025 · Rohan Pate Group OF Constructions LLP
Veda
declared completion Jul 2018 · Parshwa Developers
Vedant
declared completion Jun 2018 · Mandar Vasant Devare
Vedant
declared completion Jul 2022 · Shree Siddhivinayak Construction Group
Vedant
declared completion Mar 2022 · Vishwakarma Properties
Vedant
declared completion Jun 2023 · Chopada Landmarks

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026