MahaRERA Property Intelligence · Pune

VILLAGE RESIDENCY II BUILDING B

P52100004279 · promoter Prateek Omprakash Agrawal

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP52100004279
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Prateek Omprakash Agrawal is the promoter of record on 30 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
VILLAGE RESIDENCY II BUILDING B1G+5-

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000003350913/10/2019Anan Kiro vs Prateek Omprakash Agrawalorder passed
CC00500000004381624/12/2019SUSHEN K JADHAV vs Mr. Prateek Omprakash Agarwalorder passed
CC00500000005392221/01/2020GUMASTE VAIBHAV ACHYUT vs THE PRISTINE HORIZON with its sole proprietor MR. PRATEEK OMPRAKASH AGARWALorder passed
CC00500000005422329/05/2020ASHISH MUDALIAR vs M/s. Pristine Horizon Through its Proprietor Prateek Omprakash Agarwalorder passed
CC00500000010675219/03/2022VILLAGE RESIDENCY-II PROJECT AOP Building - A and B vs M/s. THE PRISTINE HORIZONpending / no order on file

Location, Land & Connectivity

Located at Mulshi, Pune, 412206. Per the filed land record, the plot is bounded to the north by By Nala Odha, to the south by By Land Owned Namdev Gosavi Out of S no 123, to the east by By road And Nere Gaothan and to the west by By Nala Odha. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park7 km
Baner–Balewadi belt12 km
Pune Junction / city centre23 km
Pune Int'l Airport (Lohegaon)25 km
Kharadi / EON IT Park28 km
Magarpatta / Hadapsar IT28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Prateek Omprakash Agrawal is the promoter on 4 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Prateek Omprakash Agrawal

Prateek Omprakash Agrawal
Past its declared completion datePune
Prateek Omprakash Agrawal
Past its declared completion datePune
Prateek Omprakash Agrawal
Past its declared completion datePune

Other RERA-registered projects in Bhor

Parvati Apartment
possession by Sep 2026 · Sagar Shivram Shete
Prospera County
possession by Oct 2026 · Mudraa Life Spaces PVT LTD
Aarya Green County
possession by Dec 2027 · Nirmitee Developers
Marigolds Valley
possession by Dec 2027 · Castle Dream Space
Swapnalok Nagari, Bhor, Building NO. 4
Deregistered by MahaRERA · possession by Dec 2027 · Swapnalok Developers
Villament
possession by Dec 2027 · Gangotree Homes AND Holidays

Major developers building in Bhor

Other RERA-registered projects in Pune

Village Residency III Building A
declared completion Dec 2021 · Prateek Omprakash Agrawal
Village Residency III Building B-C
declared completion Dec 2019 · Prateek Omprakash Agrawal
Villagio Toscana
declared completion Dec 2024 · Dasscon Realty Private Limited
Villament
possession by Dec 2027 · Gangotree Homes AND Holidays
Vilux Redefine
declared completion Oct 2020 · Kudale Paranjape Wastu
Vimal Kasturi
declared completion Jun 2019 · Aishwarya Vimal Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.