Adarsh Premia - Phase 1

Bengaluru South · Adarsh Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

84%construction reportedQ1 2026 filing
159units not bookedof 330 · Q1 2026 filing
30 Jun 2020declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Jun 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

4 BHK with Servent Room
50

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.9registered acres

84.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/170915/000155

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2020
Land area15,884 sq m (3.9 acres)
Homes registered330
Tower/wing entries4
Unit mix50 × 4 BHK with Servent Room

In context

Density84.1 homes per acre
Density in context62nd percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units330Total inventory registered with K-RERA.
Official carpet area209 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area15,884 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI4.54Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries4Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)330Separate filed counts; these categories may overlap and are not added together.
Open-parking field33Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date15-11-2013

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK with Servent Room50100%209 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A234646-
B239292-
C239696-
D239696-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 330 official flat/unit rows, matching the 330 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK234128.0-153.1 sqm416.0-487.0 sqm234
4BHK96186.7-230.7 sqm589.0-755.0 sqm96

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
C96141.3-147.0 sqm461.0-478.5 sqm96
D96186.7-230.7 sqm589.0-755.0 sqm96
B92128.0-144.5 sqm416.0-463.0 sqm92
A46141.7-153.1 sqm438.0-487.0 sqm46
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A101A13BHK141.7 sqm438.0 sqm1
A102A13BHK153.1 sqm487.0 sqm1
A201A23BHK141.7 sqm438.0 sqm1
A202A23BHK153.1 sqm487.0 sqm1
A301A33BHK141.7 sqm438.0 sqm1
A302A33BHK153.1 sqm487.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

  • Suit for partition — City Civil Court Bangalore (2023)

⚠ 2 of 38 compliance document slots are filed as under process / not yet usable: Proforma For Sale Deed, Brochure of Current Project.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

3 K-RERA orders on this project (PROJECT EXTENSION, PROJECT MODIFICATION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Ravi Shirish Shetye vs ADARSH dEVELOPERSInterest at 15%pa on the payment made by us, for every month of delay till handing over the possesionAUTHORITY19/05/2025
NAGARAJA HN vs Adarsh Premia- Phase1Rs18 PER CENT PER ANNUM ON THE TOTAL AMOUNT PAID BY ME, TILL THE DATE OF HANDING OVER THE FLAT WITH O.C. AND COMPLETING ALL LEGAL FORMALITIES.AUTHORITY18/07/2025
Jyothi H R vs ADARSH DEVELOPERSCompensation for the delay and interest to be paid on the amount that we have paid the buildersAUTHORITY15/06/2023
Amarnath S vs Adarsh DevelopersRefund of the advance amount paid, Rupees Five lakhs Only, along with applicable interestAUTHORITY03/12/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (4 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190212/0002077
12-02-2019
Refund of money and compensation and delay in delivery dateAdarsh Premia - Phase 1DISPOSED AO
CMP/190912/0004118
12-09-2019
Payment of interest and compensation on amounts paidAdarsh Premia - Phase 1DISPOSED AO
CMP/191205/0004891
05-12-2019
Failure to handover Flat No. B-701, 7th Floor, B-Block, Adarsh Premia within scheduled time and refund amounts paid with interest and compensationAdarsh Premia - Phase 1DISPOSED AO
CMP/210302/0007716
02-03-2021
Significant delay in construction of the apartmentAdarsh Premia - Phase 1DISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved11-12-2009BWSSB 11122009.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved18-12-2019Premia revised cfe.pdf
KSPCB- MOEF (Above 50 Acres)Approved10-07-2023Premia SEIAA new.pdf
KPTCL- BESCOMApproved31-05-2010BESCOM 31052010.pdf
Fire and SafetyApproved28-03-2015Premia FIRE 28032015.pdf
Airport Authority of IndiaApproved13-01-2024HAL 13012024.pdf

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectAtul Aggarwal-2004No10, Vittal Malya Road
ContractorSimplex Infrastructures Limited-1924S.C. Road, Anand Rao Circle
Structural engineerChetana Engineering Consultants Pvt. Ltd---

Builder track record

RERA filing

Adarsh has 18 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Adarsh Developers”) (average reported construction progress 58%). 12 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹323.87 Cr collected from buyers, ₹391.91 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹391.91 Cr) exceeded buyer collections (₹323.87 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress79% → 84% (+5 pts)
Units sold/booked as registered171/330 (52%)
Buyer collections in available QPRs₹883.95 Cr
Escrow withdrawals in available QPRs₹1,162.37 Cr (1.31x collections)
  • Construction progress moved from 79% to 84% across the filed QPR window.
  • Across available QPR rows, escrow withdrawals are 1.31x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹61.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: LAKSHMI VILAS BANK Bengaluru Main (IFSC LAVB0000161, a/c …8271). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 2 project-photo uploads.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre8 km
Electronic City14 km
Bellandur–Marathahalli belt14 km
Outer Ring Road / Manyata15 km
Whitefield IT hub21 km
Kempegowda Int'l Airport35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Adarsh Developers. View Adarsh Developers's full track record →
Adarsh Developers has 9 projects registered in Bangalore, 3 past RERA deadline.

Other projects by this builder in Bangalore

Adarsh Crest Phase 1
Past deadline · 74% built · 100% sold
Adarsh Stratuss Phase 1
Past deadline · 75% built · 93% sold
Adarsh Lake Reserva Phase 1
On track · 0% sold
Adarsh Welkin Park Villas
On track · 58% built · 66% sold

Other RERA-registered projects in Banashankari

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Adarsh Premia - Phase 1?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026